HomeMy WebLinkAbout2026-06RESOLUTION NO. 2026-06
APPROVING LAND USE PERMIT REQUEST LUP26-0003 REAPPROVING LAND
USE PERMIT DEV16-0005 TO ALLOW THE CONTINUED OPERATION OF AN
UNMANNED WIRELESS TELECOMMUNICATION FACILITY AT 156 DIABLO
ROAD (APN: 200-211-028).
WHEREAS, Tom Swarner of PEN Planning & Engineering Network (Applicant)
representing AT&T Mobility (Tenant), has requested approval of Land Use Permit request
LUP26-0003 to authorize the continued operation of an unmanned wireless
telecommunication facility located at 156 Diablo Road; and
WHEREAS, the subject site is located at 156 Diablo Road and is further identified as
Assessor’s Parcel Number 200-211-028; and
WHEREAS, the site contains an existing wireless telecommunication facility previously
approved under Land Use Permit DEV16-0005 which expired on March 8, 2026; and
WHEREAS, the Town of Danville Downtown Business District (DBD) 2: Old Town Retail
Transition and Wireless Communication Facilities Ordinances require approval of a Land
Use Permit prior to the establishment or operation of a wireless telecommunication facility;
and
WHEREAS, the project has been found to be Categorically Exempt from the requirements
of the California Environmental Quality Act (CEQA) Class 1, Section 15301; and
WHEREAS, the Planning Commission did review the project at a noticed public hearing on
March 24, 2026; and
WHEREAS, the public notice of this action was given in all respects as required by law;
and
WHEREAS, the Planning Commission did hear and consider all reports, recommendations,
and testimony submitted in writing and presented at the hearing; now, therefore, be it
RESOLVED that the Planning Commission approves Land Use Permit request LUP26-0003
subject to the conditions contained herein, and make the following findings in support of
this action:
FINDINGS OF APPROVAL
1.The land use will not be detrimental to the health, safety, and general welfare of the
Town because the existing project is in compliance with the Wireless
Docusign Envelope ID: DFFF3F14-951C-448C-BF98-AB6D55635680
PAGE 2 OF RESOLUTION NO. 2026-06
Communication Facilities ordinance.
2. The land use will not adversely affect the orderly development of property within
the Town.
3. The land use will not adversely affect the preservation of property values and the
protection of the tax base within the Town.
4. The land use will not adversely affect the policy and goals as set by the Danville
2030 General Plan as the Zoning Ordinance was written to be consistent with the
overall policy and framework of the General Plan.
5. The land use will not create a nuisance and/or enforcement problem within the
neighborhood or community as the facility is unmanned, the facility does not
generate a significant level of noise, and it provides a greater service area for
wireless communication users.
6. The land use will not encourage marginal development within the neighborhood as
the Wireless Communication Ordinance was written to preserve the unique visual
character of the Town, and has set forth design standards to regulate the type of
facility which could be installed.
CONDITIONS OF APPROVAL
Conditions of approval with an asterisk ("*") in the left-hand column are standard project
conditions of approval.
Unless otherwise specified, the following conditions shall be complied with prior to the
approval of the land use permit for the project. Each item is subject to review and approval
by the Planning Division unless otherwise specified.
A. GENERAL
1. This approval is for Land Use permit request LUP26-0003 reapproving Land
Use Permit DEV16-0005 authorizing the continued operation of an
unmanned wireless telecommunication facility at 156 Diablo Road. Except as
may be modified by these conditions of approval, development shall be
substantially as shown on the project drawings as follows:
a.Site plans, elevations, antenna plans, and simulation drawings submitted
by PEN Planning & Engineering Network, labeled “PROJECT NO:
2469U0166,” dated February 11, 2026.
Docusign Envelope ID: DFFF3F14-951C-448C-BF98-AB6D55635680
PAGE 3 OF RESOLUTION NO. 2026-06
2.Within two weeks of this approval, the applicant shall reimburse the Town
for notifying surrounding residents. The fee shall be $272.64 ($138 plus 153
notices x $0.88 per notice).
* 3. The applicant shall obtain a building permit from the Town’s Building
Division prior to installation of new equipment.
* 4. The applicant shall pay or be subject to any and all Town and other related
fees pertaining to the use associated with this Land Use Permit. These fees
shall be based on the current fee schedule in effect at the time the relevant
permits are secured, and shall be paid prior to issuance of said permit.
* 5. The project shall be maintained as approved. Minor modifications to the
design, but not the use, may be approved by staff. Any other change will
require Planning Commission approval through a separate Land Use Permit
application.
* 6. The applicant shall allow additional wireless communication companies to
collocate antenna equipment and antennas at this site, subject to review and
approval by the Planning Commission under a separate Land Use Permit
and/or Development Plan application. The applicant and other wireless
carriers shall provide a mechanism for the construction and maintenance of
shared facilities and infrastructure and shall provide for equitable sharing of
costs. Construction of future facilities shall not interrupt or interfere with the
continuous operation of the applicant’s facilities.
7. This Land Use Permit will be valid for ten (10) years and shall expire on
March 24, 2036. Time extensions may be approved by the Chief of Planning,
upon the receipt of a letter requesting the extension by the applicant and
shall be determination at the discretion of the Chief of Planning. The
extension request may be referred to the Planning Commission for
consideration and action.
* 8. All equipment associated with the wireless communication facility shall be
removed within 30 days of the discontinuation of the use and the site shall be
restored to its original pre-construction condition. Prior to installation of the
facility, the service provider shall submit to the Town a letter stating the
provider’s agreement to remove the equipment within 30 days of
discontinued use of the facility. In addition, the service provider shall
provide the Town with a notice of intent to vacate the site a minimum of 30
days prior to the vacation.
Docusign Envelope ID: DFFF3F14-951C-448C-BF98-AB6D55635680
PAGE 4 OF RESOLUTION NO. 2026-06
9. All equipment shall be painted a non-reflective color to blend with the
surrounding environment. The visual appearance of all equipment shall be
maintained in their approved condition.
* 10. At any time during the effectiveness of this approval, the approval shall be
revocable for cause in accordance with sections 26-2.2022 and 418.1 of the
Danville Municipal Code, including failure to comply with these conditions
of approval if the permittee has caused or permitted any public nuisance in
connection with the use.
APPROVED by the Danville Planning Commission at a regular meeting on March 24, 2026,
by the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
_____________________________
CHAIR
APPROVED AS TO FORM:
_______________________________ ______________________________
CITY ATTORNEY CHIEF OF PLANNING
Bowles, Graham, Halker, Maddalon, Palandrani, Radich, TrujilloNone