HomeMy WebLinkAbout021726-08.6 ADMINISTRATIVE STAFF REPORT 8.6
TO: Mayor and Town Council February 17, 2026
SUBJECT: Resolution No. 11-2026, awarding a construction contract and transferring
funds from CIP No. C-305 to the Iron Horse Trail Crossing Improvements,
Project No. C-607
BACKGROUND
The Town’s Capital Improvement Program (CIP) includes the Iron Horse Trail Crossing
Improvements, Project No. C-607. This project will provide for the construction of raised
crosswalks at the Iron Horse Trail crossings at Paraiso Drive, El Capitan Drive and
Greenbrook Drive. The project includes pavement markings, signage, relocation of existing
Rectangular Rapid Flashing Beacon (RRFB) infrastructure, and associated drainage
improvements. The project also includes the placement of a new high-visibility crosswalk
at the Iron Horse Trail crossing of Sycamore Valley Road.
The project is funded with a combination of a Community Project Funding Federal Earmark
in the amount of $350,000, Measure J Return to Source funds, and Capital Improvement
Program General Improvement Funds, including a fund transfer from Project No. C-305.
Design of the project has been completed and a Request for Authorization for the
Construction Phase along with an Encroachment Permit were previously approved by the
California Department of Transportation. With these steps finalized, the project is now
ready to move into the construction phase following the award of a construction contract.
DISCUSSION
A total of ten (10) bids were received and opened on February 5, 2026. The apparent low bid
was submitted by BuildCorp Inc. of San Francisco, CA with a bid of $428,570.00. Bid results
are summarized in Attachment C. The Engineer’s Estimate was $398,300.00. Construction
is scheduled to begin in April 2026 with an anticipated completion timeline of July 2026.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public. Copies of the staff
report and all attachments have been provided to BuildCorp Inc. to allow them to review
the materials prior to the Town Council hearing.
Award of Contract February 17, 2026
Iron Horse Trail Crossing Improvements
CIP C-607 2
FISCAL IMPACT
The low bid amount of $428,570.00 plus a 10% contingency amount of $42,857.00 results in
a total construction budget of $471,427.00. A transfer from CIP No. C-305 Traffic
Management Program in the amount of $65,522.90 is needed to fully fund the project.
RECOMMENDATION
Adopt Resolution No. 11-2026, awarding a construction contract and transferring funds
from CIP No. C-305 to the Iron Horse Trail Crossing Improvements project, CIP No. C-607.
Prepared by:
Soren Fajeau, P.E.
Traffic Engineering Associate
Reviewed by:
Diane J. Friedmann
Development Services Director
Attachments: A - Resolution No. 11-2026
B – CIP Page No. C-607
C – CIP Page No. C-305
D – Bid Results Summary
RESOLUTION NO. 11-2026
AWARDING A CONSTRUCTION CONTRACT AND TRANSFERRING FUNDS
FROM CIP NO. C-305 TO THE IRON HORSE TRAIL CROSSING
IMPROVEMENTS PROJECT, CIP NO. C-607
WHEREAS, the Danville Town Council previously appropriated funding for the Iron Horse
Trail Crossing Improvements, CIP No. C-607 in the adopted 2025/26 Capital Improvement
Program; and
WHEREAS, the project will consist of the construction of new raised crosswalks and
associated drainage improvements at the Iron Horse Trail crossings of Paraiso Drive, El
Capitan Drive and Greenbrook Drive, and the placement of a high visibility crosswalk at
the Iron Horse Trail Crossing at the intersection of Sycamore Valley Road; and
WHEREAS, bids were solicited from contractors for this project; and
WHEREAS, the City Clerk of this Town did, in open session on the 5th day of February,
2026, publicly open and read aloud the sealed bids received as required by law; and
WHEREAS, sufficient funds have been budgeted in the Capital Improvement Program for
the construction phase of Iron Horse Trail Crossing Improvements, CIP C-607; now,
therefore, be it
RESOLVED, by the Danville Town Council, that funds in the amount of $65,522.90 be
transferred from Traffic Management Program (CIP No. C-305) to Iron Horse Trail Crossing
Improvements (CIP No. C-607) to fund construction of the project; and be it further
RESOLVED, by the Danville Town Council, that the Town Manager be and hereby is
authorized to execute, on behalf of the Town, a written contract with BuildCorp Inc. for
$428,570.00 and authorize use of a 10% contingency not-to-exceed $42,857.00 for a total
construction budget of $471,427.00 for work in connection therewith, and the City Clerk is
hereby directed to attest same and affix thereto the official seal of the Town; and, be it further
RESOLVED, by the Danville Town Council, that staff shall within five (5) days of the
adoption of this resolution transmit an Extract of Public Works contract award to the
Department of Industrial Relations, Division of Apprenticeship Standards, P.O. Box 420603,
San Francisco, CA 94142. (Note: Should a finding of any discrepancy regarding this ratio of
apprentices to journeymen be made, the Town shall notify the Division of Apprenticeship
Standards of such findings.)
Docusign Envelope ID: 1019FE83-8FC4-4138-9F32-43CFFA9FD90E
ATTACHMENT A
PAGE 2 OF RESOLUTION NO. 11-2026
APPROVED by the Danville Town Council at a regular meeting on February 17, 2026, by
the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
______________________________
MAYOR
APPROVED AS TO FORM: ATTEST:
_______________________________ ______________________________
CITY ATTORNEY CITY CLERK
Docusign Envelope ID: 1019FE83-8FC4-4138-9F32-43CFFA9FD90E
Town of Danville www.danville.ca.gov • CIP 108
Iron Horse Trail Crossing
Improvements
CIP Project: C-607
Department/Division: Transportation
Type: New (or Modified New) Project
Status:
Completed Phases:
2022/23
◦$350,000 Federal Community Grant Awarded
2023/24
◦Project Design
Future Phase:
2025/26
◦Construction
Description:
The Iron Horse Trail Crossing Improvements Project includes constructing raised crosswalks at IHT crossings
on Paraiso Drive, El Capitan Drive and Greenbrook Drive. The project includes pavement markings, signage and
drainage improvements. Coordination with East Bay Regional Parks District will be required. Project also includes
improving the IHT/Sycamore Valley Road crossing with high-visibility crosswalk pavement markings, separated
ped/bicycle crosswalks, curb/sidewalk improvements, and miscellaneous traffic signal improvements.
Project Cost Estimate:
Prior Years 2025/26 2026/27 2027/28 2028/29 2029/30
Design/Plan Review $82,610 $0 $0 $0 $0 $0
Construction $372,000 $95,000 $0 $0 $0 $0
Inspection & Admin. $26,000 $0 $0 $0 $0 $0
Total Cost Estimate: $480,610 $95,000 $0 $0 $0 $0
Total Expenditure: ($65,523)
Unexpended as of 4/8/25: $415,087
Project Appropriation and Funding:
Prior Years 2025/26 2026/27 2027/28 2028/29 2029/30
CIP Gen Purpose Rev $60,610 $95,000 $0 $0 $0 $0
Federal Earmark $350,000 $0 $0 $0 $0 $0
Meas J Rtrn to Src $70,000 $0 $0 $0 $0 $0
Total Funding: $480,610 $95,000 $0 $0 $0 $0
ATTACHMENT B
ATTACHMENT C
PROJECT: Iron Horse Trail Crossing Improvements,
Contract No. C-607
BID OPENING: February 5, 2026, at 2:00 p.m. PST
Please direct all questions regarding this bid opening to:
Soren Fajeau, P.E., Traffic Engineering Associate, (925) 314-3381
sfajeau@danville.ca.gov
Number of Addendums: 1
OFFICIAL BID RESULTS
CONTRACTOR BID AMOUNT
Buildcorp Inc.* $428,570.00
Terocons $485,180.00
CPE Inc. $523,465.00
QLM Inc. $536,530.00
EE Gilbert Construction $620,951.63
Spencon Construction $644,805.00
FBD Vanguard Construction $654,807.00
Sposeto Engineering $685,812.00
Kerex Engineering $759,320.00
RNR Paving $868,471.00
*Lowest Responsive Bid
I, Marie Sunseri, City Clerk for the Town of Danville, do hereby affirm that the bids
received were not opened prior to the time of the public bid opening.
ATTACHMENT D