HomeMy WebLinkAbout081225-06.7 ADMINISTRATIVE STAFF REPORT 6.7 TO: Mayor and Town Council August 12, 2025 SUBJECT: Resolution No. 58-2025, awarding a professional services agreement for construction management and inspection services during the construction of Diablo Road Trail and Drainage Improvements Project No. C-055 BACKGROUND The Diablo Road Trail and Drainage Improvements Project, CIP No. C-055, is progressing according to schedule with construction anticipated to begin Fall 2025. As with previous complex large-scale Town infrastructure projects, the Town intends to utilize an independent construction manager and inspector to support the efforts of in-house Engineering staff and ensure that construction activities are completed on schedule and within the established project budget. The Request for Qualifications period for construction management and inspection services closed on July 25, 2025. DISCUSSION In response to the Town's solicitation, five (5) responses from construction management consultants were received. After a thorough review of the qualifications, a committee consisting of Town staff and the project engineer selected two firms which were interviewed on July 30, 2025. The firm identified as the best qualified to provide the desired construction management and inspection services is Haley & Aldrich of Walnut Creek, California. Haley & Aldrich has considerable experience with similar projects and has submitted a fee proposal that addresses the Town's needs within the constraints of the allocated funding. PUBLIC CONTACT Posting of the meeting agenda serves as notice to the general public. FISCAL IMPACT The cost for construction management and inspection services is $450,000 with a 5% contingency of $22,500 for a total of $472,500. Funds are available in the Diablo Road Trail and Drainage Improvements Project, CIP No. C-055 (Attachment B). Construction Management and 2 August 12, 2025 Inspection Services RECOMMENDATION Adopt Resolution No. 58-2025, awarding a professional services agreement for construction management and inspection services during the construction of Diablo Road Trail and Drainage Improvements Project No. C-055. Prepared by: Allan Shields Transportation Manager Reviewed by: Robert B. Ewing for Diane J. Friedmann City Attorney Diane J. Friedmann Development Services Director Attachments: A - Resolution No. 58-2025 B - CIP Page No. C-055 RESOLUTION NO. 58-2025 AWARDING A PROFESSIONAL SERVICES AGREEMENT FOR CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES DURING THE CONSTRUCTION OF DIABLO ROAD TRAIL AND DRAINAGE IMPROVEMENTS PROJECT, NO. C-055 WHEREAS, the Town is undertaking construction of the Diablo Road Trail and Drainage Improvements Project, CIP No. C-055; and WHEREAS, the utilization of independent construction management and inspection services will support efforts to complete the project both on schedule and within the established budget; and WHEREAS, a Request for Qualifications was solicited and the Town received 5 consultant responses by the July 25, 2025, deadline; and WHEREAS, two firms were interviewed the week of July 28, 2025; and WHEREAS, Haley & Aldrich was identified as the firm most qualified to provide the desired construction management and inspection services and a scope of work and related fee proposal has been negotiated; now, therefore, be it RESOLVED, by the Danville Town Council that the Town Manager is hereby authorized to execute, on behalf of the Town, a Professional Services Agreement with Haley & Aldrich with a not-to-exceed budget of $450,000, and that the Town Manager be authorized to establish and utilize a 5% contingency in the amount of $22,500 for additional work that may be subsequently approved by contract amendment. APPROVED by the Danville Town Council at a regular meeting on August 12, 2025, by the following vote: AYES: NOES: ABSTAINED: ABSENT: _____________________________________ MAYOR APPROVED AS TO FORM: ATTEST: ________________________________ ______________________________________ CITY ATTORNEY CITY CLERK Docusign Envelope ID: 269B04B1-D57F-453D-95DD-4346CFDEC80F ATTACHMENT A CIP 89 • 2025–2026 Operating Budget & Capital Improvement Program Projects Diablo Road Trail from Alameda Diablo to Tank Access Road CIP Project: C-055 Department/Division:Transportation Type: New (or Modified New) Project Status: Completed Phases: 20222/23 ◦Environmental MND/IS approved 2023/24 ◦Redesign of Trail Segments due to 2022/23 winter storms, regulatory approval Future Phases: 2025/26 ◦Construction to begin Description: The Diablo Road Trail from Alameda Diablo to Tank Access Road Project is part of the North East Roadway Improvement Assessment District (NERIAD) and consists of construction of a paved 0.9-mile Class I pedestrian/ bicycle path located adjacent to the south side of Diablo Road from Fairway Drive to the west to the tank access road (1,200 feet west of Mt. Diablo Scenic/Blackhawk intersection) to the east. Path will connect to existing 0.5- mile Diablo Road Trail (aka Barbara Hale) to the west and a new 0.7-mile Class I path to the east, constructed as part of the Magee Preserve Development. Project Cost Estimate: Prior Years 2025/26 2026/27 2027/28 2028/29 2029/30 Design/Plan Review $910,459 $0 $0 $0 $0 $0 Construction $4,731,568 $1,700,000 $0 $0 $0 $0 Inspection & Admin. $57,200 $0 $0 $0 $0 $0 Total Cost Estimate: $5,699,227 $1,700,000 $0 $0 $0 $0 Total Expenditure: ($894,375) Unexpended as of 4/8/25: $4,804,852 Project Appropriation and Funding: Prior Years 2025/26 2026/27 2027/28 2028/29 2029/30 CIP Gen Purpose Rev $0 $1,700,000 $0 $0 $0 $0 Meas J Major St 24c $3,059,536 $0 $0 $0 $0 $0 Meas J-CC-TLC (2012) $75,000 $0 $0 $0 $0 $0 Meas J-CC-TLC (2017) $1,500,000 $0 $0 $0 $0 $0 NERIAD $914,691 $0 $0 $0 $0 $0 TDA Grant $150,000 $0 $0 $0 $0 $0 Total Funding: $5,699,227 $1,700,000 $0 $0 $0 $0 ATTACHMENT B