ADMINISTRATIVE STAFF REPORT 6.8
TO: Mayor and Town Council March 18, 2025
SUBJECT: Resolution No. 19-2025, awarding a construction contract; and
appropriating and transferring funds for the Diablo Vista Park
Playground Renovation, CIP B-560
BACKGROUND
The Capital Improvement Program (CIP) includes CIP Project B-560 which would replace
and upgrade the existing children’s play area at Diablo Vista Park. Originally scheduled
to be replaced during the 2022/23 fiscal year, the project was deferred pending a
determination of the overall project scope. The age and condition of the existing play
area are such that this feature warrants prompt attention.
The project improvements feature an updated play area with a variety of play features
for both older and younger children as well as those with limited mobility. The park’s
iconic elements such as the ‘snake’ feature and existing hill allowing a southern view are
preserved. CIP Project B-616, which would construct a multi-sport skate park, is a
separate project which would be located adjacent to the play area.
In 2021, CIP projects B-560 and B-616 were combined to proceed with design and
construction. This combined project approach was pursued because the children’s play
area and skate park sites are located adjacent to one another, and it presented an
opportunity to achieve economies of scale and more favorable construction bids.
Construction bids were solicited in Spring 2024. Only two bids were received. After
considering all the information presented, the Town Council rejected both bids at their
July 2, 2024, meeting.
The Town Council subsequently opted to proceed with re-bidding and constructing the
two projects separately. On January 16, 2025, the Town issued a call for bids for CIP B-
560 – Diablo Vista Park Playground Renovation.
DISCUSSION
Thirteen bids were received and opened on February 18, 2025. The lowest bid was
submitted by Suarez and Munoz Construction Inc., of Hayward, California, with a base
bid of $1,583,292. Three alternate bid items were also included as a part of the bid
package. The bid alternate items included:
Award of Construction Contract 2 March 18, 2025
Diablo Vista Park Playground Renovation
Alternate 1 – Play Area Shade Structure
Alternate 2 – Fitness Equipment for Adults and Seniors
Alternate 3 – Boulders
Bid results are summarized in Attachment B.
The following table summarizes the engineer’s estimate, bid plus contingency costs for
the base bid and the three bid alternates:
Engineer’s Low 10%
Estimate Bid Contingency Total
CIP B-560 - Play Area $1,941,258 $1,583,292 $158,329 $1,741,621
Alt. 1-Shade Structure $165,000 $155,000 $15,500 $170,500
Alt. 2-Fitness Equipment $82,874 $86,112 $8,611 $94,723
Alt. 3-Boulders $20,520 $26,500 $2,650 $29,150
Total $2,209,652 $1,850,904 $185,090 $2,035,994
At a special meeting held on March 5, 2025, the Senior Advisory Commission
recommended the inclusion of bid alternates 1 and 2 which would provide a shade
structure and fitness equipment for active adults and seniors. The commission further
recommended allocating previously reserved Senior Services Funds to cover the
additional cost plus contingency amounts for both bid alternates.
This report recommends awarding the construction contract to Suarez and Munoz
Construction Inc., of Hayward, California.
The cost for the base project plus bid alternate 1 and bid alternate 2 totals $1,824,404, plus
a 10% contingency amount of $182,440 yields a total construction budget of $2,006,844.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public. Before construction
begins, residents within proximity to the project will be notified by the contractor in
writing. In addition, project identification signs will be posted together with changeable
message boards.
FISCAL IMPACT
The low bid amount of $1,583,292 plus bid alternate 1 and bid alternate 2 which includes
a shade structure and fitness equipment for adults and seniors in the amount of $241,112,
totals $1,824,404, plus a 10% contingency amount of $182,440 yields a total construction
budget of $2,006,844.
Award of Construction Contract 3 March 18, 2025
Diablo Vista Park Playground Renovation
CIP B-560 currently has $1,047,282 available for construction, including $1,000,000 in
Local Fiscal Recovery Funds from the American Rescue Plan Act. An additional $959,562
is required to award this contract. The following appropriations and transfers are
recommended to fully fund the project and award a contract to Suarez and Munoz
Construction Inc.
Parkland In Lieu Fees $363,987
Transfer from CIP B-616 $330,352
Senior Services Funds $265,223
$959,562
RECOMMENDATION
Adopt Resolution No. 19-2025, awarding a construction contract; and appropriating and
transferring funds for the Diablo Vista Park Playground Renovation, CIP B-560.
Prepared by:
Bob Russell, PLA
Landscape Architect
Reviewed by:
Diane J. Friedmann
Development Services Director
Attachments: A - Resolution No. 19-2025
B – Bid Results - Diablo Vista Park Playground Renovation
C – CIP Page No. B-560
D – CIP Page No. B-616
RESOLUTION NO. 19-2025
AWARDING A CONSTRUCTION CONTRACT; AND APPROPRIATING AND
TRANSFERRING FUNDS FOR THE DIABLO VISTA PARK PLAYGROUND
RENOVATION, CIP B-560
WHEREAS, the Danville Town Council has previously included Project B-560 - Diablo
Vista Park Capital Maintenance, including the Diablo Vista Park Play Area Renovation
in the Capital Improvement Program; and
WHEREAS, the Town has determined that the project is Categorically Exempt from
requirements of the California Environmental Quality Act (CEQA); and
WHEREAS, bids were solicited from contractors for the project; and
WHEREAS, the City Clerk of this Town did, in open session on the 18th day of February,
2025, publicly open and read aloud the sealed bids received as required by law; and
WHEREAS, the low responsive bid was submitted by Suarez and Munoz Construction
Inc., of Hayward, California and the City Engineer recommends awarding a construction
contract to said contractor, based upon the base bid, bid alternate 1 and bid alternate 2;
and
WHEREAS, CIP B-560 currently has $1,047,282 available for construction, including
$1,000,000 in Local Fiscal Recovery Funds from the American Rescue Plan Act; leaving
an additional $959,562 required to award this contract based upon the base bid, bid
alternate 1 and bid alternate 2; now, therefore, be it
RESOLVED, by the Danville Town Council, that the Town award a construction contract
for Diablo Vista Park Play Area Renovation B-560, to Suarez and Munoz Construction
Inc., of Hayward, California; and, be it further
RESOLVED, by the Danville Town Council, that the Town Manager be and hereby is
authorized to execute, on behalf of the Town, a written contract with Suarez and Munoz
Construction Inc., of Hayward, California for $1,824,404, and authorize the use of a 10%
contingency not to-exceed $182,440 for a total construction budget of $2,006,844 for work
in connection therewith, and the City Clerk is hereby directed to attest same and affix
thereto the official seal of the Town; and, be it further
RESOLVED, that the Danville Town Council hereby appropriates and transfers $959,562
to construct this project, including appropriating $363,987 in Parkland In Lieu Fees,
transferring $330,352 from CIP Project B-616 Multi-Sport Skate Park, and transferring
$265,223 from Senior Services funds; and be it further
Docusign Envelope ID: 68AC43C7-2606-47C5-84A1-A90E9C92ED12
ATTACHMENT A
PAGE 2 OF RESOLUTION NO. 19-2025
RESOLVED, that staff shall within five (5) days of the adoption of this resolution,
transmit an Extract of Public Works contract award to the Department of Industrial
Relations, Division of Apprenticeship Standards, P.O. Box 420603, San Francisco, CA
94142. (Note: Should a finding of any discrepancy regarding this ratio of apprentices to
journeymen be made, the Town shall notify the Division of Apprenticeship Standards of
such findings.)
APPROVED by the Danville Town Council at a regular meeting on March 18, 2025, by
the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
________________________
MAYOR:
APPROVED AS TO FORM: ATTEST:
_________________________ ________________________
CITY ATTORNEY CITY CLERK
Docusign Envelope ID: 68AC43C7-2606-47C5-84A1-A90E9C92ED12
PROJECT: Diablo Vista Park Playground Renovation,
Contract No. B-560
BID OPENING: February 18, 2025 at 2:00 p.m. PST
Please direct all questions regarding this bid opening to:
Bob Russell, PLA, (925) 314-3315, brussell@danville.ca.gov
Number of Addendums: 2
OFFICIAL BID RESULTS
CONTRACTOR BASE BID ALTERNATIVE
1
ALTERNATIVE
2
ALTERNATIVE
3
*Suarez & Munoz
Construction Inc.
$1,583,292 $155,000 $86,112 $26,500
Guerra Construction $1,605,660.09 $159,360 $73,928.50 $49,292
GradeTech $1,705,257.87 $154,896.50 $67,579.72 $56,997.80
FrontLine Construction $1,728,661.55 $146,435.35 $146,671.78 $36,963.34
Ella $1,756,816.22 $162,000 $117,769 $23,800
McGuire & Hester $1,855,494 $161,600 $84,068 $25,040
Carone and Company $1,888,881.65 $166,740 $110,743 $102,894
Build Corp. $2,057,000 $142,857 $110,186 $6,100
Calico California $2,211,247.76 $140,000 $86,144 $53,770
Kerex Engineering $2,359,824.50 $220,000 $186,595 $53,000
MVP Construction $2,366,161 $170,535 $94,759 $52,040
S&H Construction $2,398,600 $240,600 $213,140 $60,500
Saboo Inc. $2,545,240 $340,000 $266,030 $131,000
*Lowest Responsive Bid
I, Marie Sunseri, City Clerk for the Town of Danville, do hereby affirm that the bids received were
not opened prior to the time of the public bid opening.
ATTACHMENT B
Town of Danville
www.danville.ca.gov • CIP 72
Projects
DIABLO VISTA PARK CAPITAL MAINTENANCE
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
Updated description and added funding for 2028/29.
RATIONALE FOR PROPOSED PROJECT:
Provide for ongoing repair and replacement.EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:0
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
This project has been modified from the previous year.
PROJECT APPROPRIATION AND FUNDING
This project provides ongoing maintenance of Diablo Vista Park facilities
including:
Ongoing: Major tree pruning
Sports field and pathway lighting repairs
Restroom maintenance - painting and repairs
Cyclone fence and backstop repairs
Fence painting and repairs
Safety surface repairs
Tennis/basketball court repairs
Windscreen repairs/replacement
2023/24 Playground equipment replacement design
2024/25 Playground equipment replacement, project planned in
conjunction with Skate Park (B-616) for a combined
construction budget of $3.35M
Future Projects: Replace field and court lighting with LED ($700,000)
Parking lot repairs and resurfacing
5/23/2024PRINTED ON:
CIP No:B-560 STATUS:In Design PRIORITY:2/3 PROJECT MANAGER:DC GREEN PROJECT:Yes
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalExpenditure Category
Capital Maintenance $20,000 $20,000 $20,000 $20,000$1,437,283 $1,537,283$20,000
Construction $0 $0 $0 $0$25,000 $25,000$0
$1,462,283 $20,000 $20,000 $20,000 $20,000 $20,000 $1,562,283Total Cost Estimate:
$351,986Total Expenditure:Unexpended: $1,110,296 on 05-01-2024
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalFunding Source(s)
CIP Gen Purpose Rev $500,000 $0 $0 $0 $0 $500,000$0
LLAD Zone D $26,907 $0 $0 $0 $0 $26,907$0
Park Dedication Impact $0 $20,000 $20,000 $20,000 $20,000 $100,000$20,000
Park Facilities $935,376 $0 $0 $0 $0 $935,376$0
$1,462,283 $20,000 $20,000 $20,000 $20,000 $20,000 $1,562,283Total Funding:
www.danville.ca.govCIP109
ATTACHMENT C
Town of Danville
www.danville.ca.gov • CIP 74
Projects
MULTI-SPORT SKATE PARK
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
Updated description.
RATIONALE FOR PROPOSED PROJECT:
Provide recreation facilities for residents.EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:50
Additional Town direct operating costs per year:$5,000
PROJECT COST ESTIMATE
This project has been modified from the previous year.
PROJECT APPROPRIATION AND FUNDING
The Parks, Recreation and Arts Commission recommends this as a high
priority parks project. The project is identified in the Parks, Recreation,
and Arts Strategic Plan as an important enhancement to the Parks,
Recreation, and Arts system.
2018/19: Study for potential locations will include search for a location
and a conceptual design. (COMPLETE)
2024/25: Multi-sport skate park construction, planned in conjunction
with Diablo Vista Park playground equipment replacement
(B- 560) with a combined construction budget of $3.35M
5/23/2024PRINTED ON:
CIP No:B-616 STATUS:In Design PRIORITY:1/2 PROJECT MANAGER:HRPGREEN PROJECT:No
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalExpenditure Category
Study $0 $0 $0 $0$20,000 $20,000$0
Design $0 $0 $0 $0$330,000 $330,000$0
Construction $0 $0 $0 $0$2,170,000 $2,170,000$0
$2,520,000 $0 $0 $0 $0 $0 $2,520,000Total Cost Estimate:
$178,020Total Expenditure:Unexpended: $2,341,981 on 05-01-2024
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalFunding Source(s)
ARPA $2,500,000 $0 $0 $0 $0 $2,500,000$0
CIP Gen Purpose Rev $0 $0 $0 $0 $0 $0$0
Park Facilities $20,000 $0 $0 $0 $0 $20,000$0
$2,520,000 $0 $0 $0 $0 $0 $2,520,000Total Funding:
www.danville.ca.govCIP113
ATTACHMENT D