HomeMy WebLinkAbout020425-06.6 ADMINISTRATIVE STAFF REPORT 6.6
TO: Mayor and Town Council February 4, 2025
SUBJECT: Resolution No. 6-2025, authorizing an amended professional services
agreement for engineering services for Diablo Road Pedestrian Trail
Project C-055
BACKGROUND
The Town’s Capital Improvement Program (CIP) includes the Diablo Road Trail from
Alameda Diablo to Tank Access Road, CIP Project C-055. This project consists of the
construction of a paved 0.9-mile Class I pedestrian/bicycle path located adjacent to the
south side of Diablo Road from Fairway Drive to the west of the tank access road (1,200
feet west of Mt. Diablo Scenic/Blackhawk intersection) to the east.
The environmental assessment and preliminary design phases of the Diablo Road Trail
have been successfully completed. In Spring 2023, the Town submitted applications for
environmental permits to both state and regional regulatory agencies, such as the
California Department of Fish & Wildlife (CDFW) and Regional Water Quality Control
Board (RWQCB).
To advance the project expeditiously, it has become necessary to engage an engineering
design firm with the expertise available to re-survey the affected area, update the design
of the trail’s retaining wall system to accommodate the creek bank erosion and develop
a detailed response that addresses CDFW concerns.
ENGEO, Inc. was previously contracted to complete a geohazard analysis and structural
design associated with the retaining walls required to complete the western portion of
the trail. The Town extends ENGEO, Inc. services to assist in completing the remaining
civil engineering design and environmental mitigation plan, finalizing the California
Department of Fish & Wildlife and Regional Water Quality Control Board permits, and
production of the construction bid documents.
The preliminary design of the new trail segment component is complete and is currently
in the environmental review phase. In preparation for the bidding and construction of
the trail project, there are trees within the trail alignment that must be removed before
the start of protected birds nesting period and before the project will be ready to bid.
Diablo Road Pedestrian Trail
CIP C-055 2 February 4, 2025
DISCUSSION
ENGEO, Inc. has been providing professional services to the Town for this project. To
proceed with tree removal along Diablo Road, and to complete the proposed trail
improvements design, it will be necessary to revise the scope of work for the project.
The revised scope of work will include required contractor training, pre-construction
surveys and biological monitoring in conformance with the project Lake and Streambed
Alteration Agreement (LSAA) for the tree removal contract. Additionally, the consultant
will prepare information describing the geotechnical constraints for ADA compliance
and final wall plans that will provide value engineering to several sections of the walls
to maximum extent possible.
ENGEO, Inc. has been providing professional services to the Town for this project. The
cost to revise the professional services agreement is $107,950.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public.
FISCAL IMPACT
The amount for the amended professional services agreement is $107,950. An additional
10% design contingency in the amount of $10,795 will be reserved for a total design
budget of $118,745. Sufficient funds have been appropriated in the Town’s 2024-2025
Capital Improvement Program to cover the cost of revised professional services.
Diablo Road Pedestrian Trail
CIP C-055 3 February 4, 2025
RECOMMENDATION
Adopt Resolution No. 6-2025, authorizing an amended professional services agreement
with ENGEO, Inc. for the Diablo Road Pedestrian Trail Project C-055.
Prepared by:
Bob Russell
Landscape Architect
Reviewed by:
Diane J. Friedmann
Development Services Director
Attachments: A - Resolution No. 6-2025
B - CIP Page No. C-055
RESOLUTION NO. 6-2025
AUTHORIZING AMENDED PROFESSIONAL SERVICES AGREEMENT WITH
ENGEO, INC. FOR THE DIABLO ROAD PEDESTRIAN TRAIL CIP C-055 PROJECT
WHEREAS, the Town previously entered into a professional services agreement with
ENGEO, Inc., for projects Diablo Road Pedestrian Trail, CIP C-055 project; and
WHEREAS, the Danville Town Council previously appropriated funding for Diablo
Road Pedestrian Trail, CIP C-055 project, in the adopted 2023/24 Capital Improvement
Program; and
WHEREAS, the Town submitted applications for environmental permits to both state
and regional regulatory agencies, such as the California Department of Fish & Wildlife
(CDFW) and Regional Water Quality Control Board (RWQCB); and
WHEREAS, it has become necessary to engage an engineering design firm with the
expertise available to re-survey the affected area, update the design of the trail’s retaining
wall system to accommodate the creek bank erosion and develop a detailed response that
addresses CDFW concerns; and
WHEREAS, the Town desires to continue professional services with ENGEO Inc., of San
Ramon, CA to continue with the design documents for the Diablo Road Pedestrian Trail,
CIP C-055 project; now, therefore, be it
RESOLVED, by the Danville Town Council that the Town Manager be and hereby is
authorized to execute on behalf of the Town, the Professional Services Agreement with
ENGEO Inc., of San Ramon, CA, with a not-to-exceed budget of $107,950, and that the
Town Manager be authorized to establish and utilize a 10% design contingency in the
amount of $10,795 for additional work that may be subsequently approved by contract
amendment, for a total of $118,745.
Docusign Envelope ID: 4ED5F5CD-1DA8-4D41-8640-3BA87899EDEF
ATTACHMENT A
PAGE 2 OF RESOLUTION NO. 6-2025
APPROVED by the Danville Town Council at a regular meeting on February 4, 2025, by
the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
MAYOR
APPROVED AS TO FORM: ATTEST:
CITY ATTORNEY CITY CLERK
Docusign Envelope ID: 4ED5F5CD-1DA8-4D41-8640-3BA87899EDEF
CIP 89 • 2024–2025 Operating Budget & Capital Improvement Program
ProjectsProjects
DIABLO ROAD TRAIL FROM ALAMEDA DIABLO TO TANK ACCESS ROAD
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
Updated description and funding.
RATIONALE FOR PROPOSED PROJECT:
This project mitigates the impacts of development within the
NERIAD project boundaries.
EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:0
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
This project has been modified from the previous year.
PROJECT APPROPRIATION AND FUNDING
Project is part of the North East Roadway Improvement Assessment
District (NERIAD) and consists of construction of a paved 0.9-mile Class I
pedestrian/bicycle path located adjacent to the south side of Diablo Road
from Fairway Drive to the west to the tank access road (1,200 feet west of
Mt. Diablo Scenic/Blackhawk intersection) to the east. Path will connect to
exisitng 0.5-mile Diablo Road (aka Barbara Haile) Trail to the west and a
new 0.7-mile Class I path to the east that will be constructed as part of the
Magee Preserve Development.
Funding plan is completed with reallocation of Measure J program funds
from C-578, C-598, C-600 and C-602.
A TDA grant ($150,000) was awarded for FY22 cycle for the construction
of the crossing improvements (HAWK signal) at the intersection of Diablo
Road/Fairway Drive.
2018 - Feasibility Study (COMPLETE)
2022/23 Environmental MND/IS approved (COMPLETE)
2023/24 Design
2024/25 Construction
5/23/2024PRINTED ON:
CIP No:C-055 STATUS:In Design PRIORITY:1 PROJECT MANAGER:AD GREEN PROJECT:Yes
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalExpenditure Category
Environmental Review $0 $0 $0 $0$445,923 $445,923$0
Design/Plan Review $0 $0 $0 $0$429,000 $429,000$0
Design $0 $0 $0 $0$35,536 $35,536$0
Construction $0 $0 $0 $0$4,731,568 $4,731,568$0
Inspection & Admin.$0 $0 $0 $0$57,200 $57,200$0
$5,699,227 $0 $0 $0 $0 $0 $5,699,227Total Cost Estimate:
$716,550Total Expenditure:Unexpended: $4,982,677 on 05-01-2024
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalFunding Source(s)
Meas J Major St 24c $3,059,536 $0 $0 $0 $0 $3,059,536$0
Meas J-CC-TLC (2012)$75,000 $0 $0 $0 $0 $75,000$0
Meas J-CC-TLC (2017)$1,500,000 $0 $0 $0 $0 $1,500,000$0
NERIAD $914,691 $0 $0 $0 $0 $914,691$0
TDA Grant $150,000 $0 $0 $0 $0 $150,000$0
$5,699,227 $0 $0 $0 $0 $0 $5,699,227Total Funding:
www.danville.ca.govCIP139