HomeMy WebLinkAbout012825 - 06.1 PLANNING COMMISSION STAFF REPORT 6.1
TO: Chair and Planning Commission January 28, 2025
SUBJECT: Public Scoping Session to provide input and allow public testimony
related to the preparation of an Environmental Impact Report for a P-1;
Planned Unit Development – Rezoning (PUD 24-0002), Major
Subdivision (SD 9679), and Development Plan (DEV24-0010) application.
The application proposes to subdivide a 100 acre parcel to create 20 single
family lots. The site is located at the terminus of Borica Drive and Como
Way (APN: 217-010-018 thru 012).
BACKGROUND/DESCRIPTION
The Town is in the early stages of reviewing an application by Bates Stringer Martin Hills
Ranch, LLC requesting approval of a Planned Unit Development – Rezoning , Major
Subdivision, and Development Plan application. The Planned Unit Development -
Rezoning request would rezone the 100 acre site from A-4; Agricultural Preserve District
to P-1; Planned Unit Development District. The Major Subdivision would allow the site
to be subdivided into 20 single family lots and to develop the lots with 20 single family
residences. The lots would be clustered onto a small portion of the site and the remainder
of the site would be designated as permanent open space.
During the Town’s early discussions with the applicant regarding this application, it was
determined that an Environmental Impact Report (EIR) should be required to be
prepared to study potentially significant environmental impacts which may be associated
with development of the project. Once prepared, the Draft EIR will be made available for
public review and comment. A Response to Comments – Final EIR will then be prepared.
The Town of Danville will be the Lead Agency for preparation of the EIR. The California
Environmental Quality Act (CEQA), Section 15082, states that once a decision is made to
prepare an EIR, the Lead Agency must prepare a Notice of Preparation (NOP) to inform
all responsible agencies and the public of that decision. The purpose of the NOP is to
provide responsible agencies and interested parties with sufficient information
describing the proposed project and its potential environmental effects to enable them to
make a meaningful response as to the scope and content of the information to be included
in the EIR. The purpose of this public scoping session is to allow for oral comments from
the public and from the Planning Commission regarding the scope of the EIR. The NOP
was also sent to the California State Clearinghouse for distribution to
interested/responsible State agencies and was sent to local agencies, districts, and
interested parties. Both written and oral comments are treated equally by the Town for
PUD24-0002 Scoping Session 2 January 28, 2025
the purpose of determining the scope of the EIR. The comment period for the NOP is 30
days, extending from January 21, 2025, through February 20, 2025
ENVIRONMENTAL REVIEW
A Draft Environmental Impact Report (EIR) will be prepared to analyze any potential
environmental impacts and associated mitigation measures.
During the 30-day Notice of Preparation (NOP) public review period, people are
encouraged to provide comments regarding the scope and content of the Draft EIR, a
document which addresses potential environmental issues and proposed mitigation
measures.
PUBLIC CONTACT
Public notice of the January 28, 2025, hearing was mailed to property owners within 750
feet and posted online. A total of 204 notices were mailed to surrounding property
owners.
RECOMMENDATION
Conduct a Public Scoping Session to provide input and allow public testimony related to
the preparation of an Environmental Impact Report for a P-1; Planned Unit Development
– Rezoning (PUD 24-0002), Major Subdivision (SD 9679), and Development Plan (DEV24-
0010) application. The application proposes to subdivide a 100 acre parcel to create 20
single family lots. The site is located at the terminus of Borica Drive and Como Way
(APN: 217-010-018 thru 012).
Prepared by:
David Crompton
Chief of Planning
Attachments: A – Notice of Preparation
B – Public Notification & Notification List
Town of Danville
Notice of Preparation and Notice of Public Scoping Meeting
Martin Hills Ranch Residential Project
Date: January 21, 2025
To: State Clearinghouse and Interested Public Agencies, Parties, and Organizations
From: David Crompton, Chief of Planning, Town of Danville Planning Division
Subject: Notice of Preparation of an Environmental Impact Report for the Martin Hills Ranch
Residential Project and Notice of Public Scoping Meeting
NOTICE IS HEREBY GIVEN THAT the Town of Danville (Lead Agency and Town ) will prepare a Draft
Environmental Impact Report (Draft EIR) for the proposed Martin Hills Ranch Residential Project
(proposed project). The Draft EIR will address the potential physical and environmental effects of the
proposed project for each of the environmental topics outlined in the California Environmental
Quality Act (CEQA) Appendix G thresholds. The Town will use the Draft EIR when considering
approval of the proposed project. Pursuant to CEQA Guidelines Section 15082, the project
description, location, and potential environmental effects of the proposed project are described in
the attached materials and available on the project website at https://danvilletowntalks.org/private-
land-development.
30-DAY NOTICE OF PREPARATION COMMENT PERIOD: The Town is soliciting comments from public
agencies, organizations, and members of the public regarding the scope and content of the Draft EIR
and the environmental issues and alternatives to be addressed in the Draft EIR. In accordance with
the time limits established by CEQA, the Notice of Preparation (NOP) public review period will begin
on January 21, 2025, and will end on February 20, 2025. Please provide your written/typed
comments (including name, affiliation, telephone number, and contact information) to David
Crompton via email at dcrompton@danville.ca.gov or mail to the address shown below by 5:00 p.m.,
on Friday, February 20, 2025. If you wish to be placed on the notification list for this proposed
project or need additional information, please contact:
David Crompton, Chief of Planning
Town of Danville, Planning Division
500 La Gonda Way
Danville, CA 94526
Phone: 925.314.3349
Email: dcrompton@danville.ca.gov
PUBLIC SCOPING MEETING: The Town will hold a Public Scoping Meeting to: (1) inform the public
and interested agencies about the proposed project; and (2) solicit public comment on the scope of
the environmental issues to be addressed in the Draft EIR as well as the range of alternatives to be
evaluated. The meeting will be held on Tuesday, January 28, 2025, during the Town ’s regularly
scheduled Planning Commission Meeting starting at 5:00 p.m. The Planning Commission Meeting
will be held at the following location:
ATTACHMENT A
Danville Town Meeting Hall
201 Front Street
Danville, CA 94526
Information regarding the Planning Commission meetings, agendas, and meetings as well as
instructions for submitting public comments at in-person meetings is available at the following
website: https://www.danville.ca.gov/129/Meetings-Agendas-Minutes. Please contact the City Clerk
at 925.314.3401 or email cityclerk@danville.ca.gov with any additional questions.
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 3
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
MARTIN HILLS RANCH RESIDENTIAL PROJECT
Project Location and Setting
Location
Regional
The Town is located in the eastern San Francisco Bay Area of Northern California. The Town is
bordered to the north by the unincorporated community of Alamo, to the east by the
unincorporated communities of Blackhawk and Diablo, to the south by the City of San Ramon, and to
the west by the Las Trampas Regional Wilderness Park and unincorporated Contra Costa County
(Exhibit 1). Located in southwestern Contra Costa County, the Town covers approximately 18 square
miles and has historically been a suburban community serving major employment centers to the
west (e.g., the City of San Francisco) and to the south (e.g., the City of San José). Regional access to
the Town is provided by Interstate 680 (I-680) and State Route (SR) 24 to the west and I-580 to the
south.
Local Setting
The approximately 102-acre project site is located off Borica Drive and Como Way; however,
development under the proposed project would only occur within 29 acres in the southeastern
portion of the site (Exhibit 2). The project site does not currently have a street address but can be
accessed at the eastern ends of Borica Drive and Como Way. The project site consists of five
Assessor’s Parcel Numbers (APNs): 218-010-008, 218-010-009, 218-010-010, 218-010-011, and 218-
010-012.
Presently, the project site is vacant and varies topographically. The northeastern and western
portions of the project site are steep and hilly with a relatively flat plateau at the highest point of the
project site. The northern and eastern portions of the project site contain some small ravines and
natural drainage features following the natural drainage downward. Overall, the project site has a
total elevation gain of approximately 165 feet from the lowest portion of the project site in the
southeast, which is approximately 590 feet above mean sea level (AMSL) to the highest point of the
project site, approximately 754 feet AMSL.
The project site is located within the Diablo, California United States Geological Survey (USGS) 7.5-
minute Topographic Quadrangle Map (Latitude 37° 47' 54.15" North; Longitude 121° 57' 30.94"
West).
12
29
37
4 4
C o n t r a C o s t a C o u n t y
A l a m e d a C o u n t y
580
92
24
680
780
160
CarquinezStrait
80
80
Mount DiabloState Park
Napa County
Solano County
580
80
Solano
C
o
u
n
t
y
Vallejo
Richmond
San Pablo
Pinole Martinez
Pleasant Hill
LafayetteOrinda
El Cerrito
Albany
Berkeley
MoragaPiedmont
Oakland
Alameda
Walnut Creek
Concord
Clayton
Pittsburg
Benicia
Denverton
Cordelia
Alamo
Danville
San Ramon
Dublin
Pleasanton LivermoreFairview
Hayward
San Leandro
Antioch
Bay Point
242
680
680
13580
880
Oakland International Airport
N
a
p
a
R
i
v
e
r
Exh ibit 1Region al Location Map
5 0 52.5
Miles
Text
Project Site
Source: Cen sus 2000 Data, Th e Californ ia Sp atial In formation Library (CaSIL).
TOWN OF DANVILLEMARTIN HILLS RANCH RESIDENTIAL PROJECT NOTICE OF PREPARATION
59600001 • 01/2025 | 1_ region al.mxd
Project Site
San Francisco County
San Mateo County
Legend
Town of Danville
59600001 • 01/2025 | 2_ local_ vicin ity.mxd
Exhibit 2Local Vicin ity Map
Source: Bin g Aerial Imagery. Coun ty of Con tra Costa. CBG Civil En gin eers, Jan uary 2025
TOWN OF DANVILLEMARTIN HILLS RANCH RESIDENTIAL PROJECT NOTICE OF PREPARATION
1,000 0 1,000500
Feet
Legend
Project Site
Off-site Improvement Area
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 6
Https://adecinnovations.sharepoint.com/sites/ESSite/Shared Documents/ES/Active Projects/5960 Bates Stringer - Martin Hills Ranch LLC/0001 Danville Martin Hills Ranch/Documents/01_EIR/00 - Notices/01_NOP/Martin
Hills Ranch NOP_01172025.docx
Existing Land Use Designation and Zoning
The project site is designated Agriculture by the Town of Danville 2030 General Plan (2030 General
Plan). In 1997, the Williamson Act Contracts that applied to the project site expired and were not
renewed. However, the expiration of the Williamson Act Contracts were not propery recorded;
therefore, when the current General Plan was adopted, the properties under this land use designation
were incorrectly identified as bound by Williamson Act Contracts to remain in agricultural use. The
Town officially filed the expiration of the Williamson Act Contract on August 21, 2024.
While the property is still zoned A-4, because the project site’s Williamson Act Contract has expired,
the site is entitled to return to the A-2, General Agricultural Zoning District, which applied prior to
the Willamson Act Contract. The A-2 district permits all types of agriculture, including farming,
horticultural, and livestock production, other agricultural uses, such as sheds, warehouse, and
granaries, and a detached single-family dwelling and accessory structures on each parcel. The A-2
district allows residential uses at a density of one unit per 5 acres.
Surrounding Land Uses
The project site is surrounded by the following land uses:
North
The General Plan designates the vacant land immediately north of the project site as Residential,
Single-family–Rural Residential (Rural Residential), as well as General Open Space, and the existing
single-family homes north of the project site as Residential, Single-family–Country Estate (Country
Estate), and Residential, Single-family–Low Density (SFL).
South
The General Plan designates the vacant lands south of the project site as General Open Space and
the existing single-family homes farther south of the project site as Residential, Single-family–
Medium Density (SFM).
East
The General Plan designates the vacant lands east of the project site as Rural Residential and
General Open Space.
Wes t
The General Plan designates the existing single-family homes west of the project site as SFL and SFM.
Project Description
Proposed Residential Project
The project applicant proposes to construct 20 single-family homes, with approximately 25 percent
(five homes) being designed with accessory dwelling units (ADUs) (Exhibit 3). The residential lots
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 7
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
would be clustered in the southeastern portion of the approximately 102-acre project site. The
proposed project is expected to generate approximately 70 residents.1,2
The 20 residential lots would range between 14,553 square feet and 25,387 square feet and the
proposed project would also include several agricultural lots located north and west of the
residences. Furthermore, the proposed project would construct project access off Como Way and
internal streets to provide internal circulation within the project site.
Land Use Designation and Proposed Zoning
The proposed project includes the development of 20 residential lots and 5 ADUs. The site’s General
Plan land use designation is Open Space–Agricultural. The Town’s A-2; General Agricultural District is
listed as Consistent with this land use designation. As previously discussed, the project site’s
Williamson Act Contract was not renewed; therefore, its underlying zoning district would apply to
the proposed project. The applicable A-2 District permits one dwelling unit per 5 acres. Given that
the project site is approximately 102 acres, the existing zoning for the project site would allow up to
20 residential lots. However, because the project applicant proposes to cluster the residential lots in
the southeast corner of the project site, the proposed project would require a rezone to Planned
Unit Development District (P-1).
The Town’s 2030 General Plan includes the subject “Elworthy East/Bolero” site as a Special Concern
Area, and provides additional direction to guide development of the site. Language within the
Special Concern Area acknowledges the limited development potential of the site, and requires that
that steeper slopes and ridgeline areas be preseved as permanent open space.
Site Access, Circulation, and Parking
Vehicle
The project site would be accessed via a proposed private extension of Como Way at the
southwestern corner of the project site that would serve all of the proposed lots within the
proposed project. There would be one cul-de-sac off the proposed Como Way extension that would
serve Lots 13, 14, 15, and 16 (Court A). The proposed Como Way extension would terminate at the
northeastern corner of the residential development area near Lots 9, 10, 11, and 12. In addition to
the two- to three-car garages attached to each proposed single-family home and the parking
available within the driveway, the proposed project would also provide 10 parking spaces on internal
streets. Specifically, two on-street parking stalls would be provided in front of Lot 18, two on-street
parking stalls would be provided in front of Lot 16, four on-street parking stalls would be provided in
front of Lots 12 and 13, and two on-street parking stalls in front of Lot 8.
1 Project population calculated by multiplying the total number of dwelling units (19 single-family homes and five ADUs) by the
Town’s average household size of 2.75 persons (24 x 2.75 = 66).
2 United States Census Bureau. 2024. QuickFacts: Danville own, California. Website:
https://www.census.gov/quickfacts/fact/table/danvilletowncalifornia/INC110222. Accessed July 11, 2024.
59600001 • 01/2025 | 3_site_plan.m xd
Exhibit 3 Site Plan
So urce: Bing Aerial Im agery. CBG Civil Engineers, January 2025
TOWN OF DANV ILLEMARTIN HILLS RANCH RESIDENTIAL PROJECT NOTICE OF PREPARATION
350 0 350175
Feet
Legend
Project Site
Off-site Improvement Area
Limit of Disturbance Area
4
5
6
7
8 9 10
11
1213
14 15
16
1718
19
20
3
2
1Basin
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 9
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
Access for emergency response vehicles would also be provided by a fire trail extending from Borica
Drive on the northwestern portion of the project site and from a proposed extension of Como Way
on the southwestern portion of the project site. Additionally, in accordance with Fire Department
requirements, fire apparatus roads with adequate width and turnaround provisions would also be
provided on-site.
Transit
Bus
Bus transit services in the vicinity of the project site are provided by County Connection. County
Connection provides bus service to and from the Dublin/Pleasanton and Walnut Creek Bay Area
Rapid Transit (BART) Stations to the Town, including the Sycamore Valley Park and Ride.
Rail
BART is a regional rail transit service that operates within the County and provides connections to
Contra Costa, San Francisco, Alameda, and San Mateo counties. The nearest BART stations are the
Dublin/Pleasanton BART Station, approximately 7.46 miles south of the project site, and the Walnut
Creek BART Station, approximately 9.48 miles northwest of the project site.
Bicycle and Pedestrian
Currently, there are no existing bicycle lanes on Como Way adjacent to the project site. The nearest
bicycle route to the proposed project is a Class III bicycle route along El Capitan Drive, connecting to
Camino Ramon and Crow Canyon Road, approximately 700 feet west of the project site. In addition,
the Iron Horse Regional Trail, which connects to the Class III bicycle route on El Capitan Drive, is
located approximately 1 mile west of the project site. The Iron Horse Regional Trail provides a
multiuse bicycle/pedestrian pathway, running from the City of Pleasanton to the City of
Concord. Pedestrian sidewalks currently exist along Como Way and the streets in the project vicinity.
No sidewalks would be provided along the proposed extension of Como Way.
Landscaping
The proposed project would plant a total of 137 trees, including 16 different tree species. Trees
would be planted along the proposed extension of Como Way, including within the median of Court
A and the terminus of the proposed extension of Como Way and along the edges of the proposed
bioretention areas at the entrance to the proposed development. Landscaping alongside roadways
would consist of drought-tolerant trees species requiring minimal irrigation, fertilization, and
maintenance.
Utilities
Domestic Water
Water service to the project site would be provided by the East Bay Municipal Utility District
(EBMUD). Water service to the project site would be provided by a connection to proposed off-site
8-inch diameter water lines in the southwest corner of the project site. Water service throughout the
project site would be provided in 8-inch diameter water lines under the proposed internal streets.
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 10
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
Stormwater Drainage
The proposed project would connect to an existing 15-inch storm drain within Como Way. Storm
drains would range from approximately 12 inches to 24 inches within the project site. The proposed
project would include two drainage management areas (DMAs), including two bioretention areas, as
stormwater treatment features:
• DMA 1: DMA 1 would include the residential lots and the majority of the internal roadways,
totaling approximately 10.56 acres. DMA 1 would include one bioretention area (Bioretention
Area 1) located along the north side of the proposed extension of Como Way, directly west of
Lot 1, totaling approximately 10,560 square feet. DMA 1 would be routed to a new outfall in
the eastern channel of the project site.
• DMA 2: DMA 2 would include an approximately 2.80-acre area just west of the existing
terminus of Como Way. It would contain one approximately 1,140-square-foot bioretention
area (Bioretention Area 2) located just south of the proposed Como Way extension at the
entrance of the proposed development. DMA 2 would drain to an existing storm drain within
Como Way.
Additionally, the proposed project would also construct a debris berm and V-ditch in the western
boundary adjacent to existing homes.
Sanitary Sewer
Sanitary sewer service for the proposed project would be provided by Central Contra Costa Sanitary
District (Central San). Sanitary sewer service to the project site would be provided by a connection to
proposed off-site 8-inch diameter sewer lines in the southwest corner of the project site. Sanitary
sewer service throughout the project site would be provided in 8-inch diameter sanitary sewer lines
under the proposed internal streets.
Solid Waste and Recycling Collection
The proposed project would be served by Republic Services, which provides recycling and solid
waste collection to the Town through Central Contra Costa County Solid Waste Authority
(RecycleSmart). RecycleSmart provides solid waste services for Central Contra Costa County
residents and businesses and is contracted with Republic Services for the collection, transfer, and
disposal of garbage, recycling, and organics.
Power and Telecommunications
Electric and gas services for the proposed project would be provided by Pacific Gas and Electric
Company (PG&E). The proposed project would connect to existing utility lines in Como Way. AT&T
would provide phone services, and Comcast would provide phone and high-speed internet services.
Phasing and Construction
The proposed project would be constructed in one phase beginning in Summer 2026 and would take
approximately 12–15 months to complete, dependent on when the sale of proposed dwelling units
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 11
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
Project Objectives
The project objectives and underlying purposes of the proposed project are to:
• Convert a vacant, underutilized property into a residential development in alignment with the
Town of Danville’s General Plan.
• Generate new, additional property tax revenues for the Town of Danville through the
conversion of unused property.
• Provide high-end homes to create a move-up large lot community.
• Create a private community of homes nestled in a secluded environment surrounded by open
space.
• Create a residential community surrounded by the site’s ridges, which will remain as open
space or potentially be farmed to enhance the homes’ secluded location.
• Provide stormwater and residential water run-off consistent with the existing natural site
drainage.
• Promote land use compatibility with neighboring residential uses by the development of
compatible housing product density to nearby existing residential development.
• Provide a circulation system that minimizes the number of homes to lessen any traffic impacts
to existing neighborhoods.
• Provide an infrastructure system, including sewer, water, and storm drain systems, that will
adequately serve full buildout of the proposed project.
• Provide adequate off-street parking for all on-site uses so as not to impact the development’s
neighbors.
• Provide for the development to have adequate separation from existing neighbors.
• Provide improved drainage and potential slide protection from the project’s property for the
adjacent neighborhood.
• Meet the objectives of the Town of Danville for new housing.
• Provide affordable housing consistent with the Town of Danville’s affordable housing
requirements by the use of Accessory Dwelling Units or Lock-off Units.
• Enhance the living experience in adjacent neighborhoods by use of an architectural character
and style that is consistent with the character of neighboring communities and the Town of
Danville.
• Provide additional character and sense of arrival to the community by providing a long
(approximately 1,000 feet) landscaped entry road.
• Provide signage and entry monumentation and landscape feature to announce the entry to
the development.
• Preserve Town of Danville’s protected ridgeline.
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 12
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
• Maintain the existing natural beauty by preserving the site’s existing creek and establishing
grading setbacks to accomplish preservation.
• Avoid protected wetlands or provide wetland mitigation measures.
• Repair landslides on the project site.
Required Discretionary and Ministerial Approvals
Discretionary approvals and permits are required by the Town of Danville for implementation of the
proposed project. The proposed project would require the following discretionary approvals and
actions, including:
• Approval of the Final EIR
• Approval of a Development Plan application
• Approval of a Vesting Tentative Map
• Approval of Rezoning application, rezoning the site from A-4, Agricultural Preserve District, to
P-1, Planned Unit Development District.
Subsequent ministerial actions would be required for the implementation of the proposed project
including issuance of grading and building permits.
A number of other agencies in addition to the Town of Danville will serve as Responsible and Trustee
Agencies, pursuant to CEQA Guidelines Section 15381 and Section 15386, respectively. These
agencies may include, but are not limited to, the following:
• United States Fish and Wildlife Service (USFWS)
• California Department of Fish and Wildlife (CDFW)
• EBMUD
• PG&E
• United State Army Corps of Engineers (USACE)
• California State Water Resources Control Board (State Water Board)
• Central San
• San Ramon Fire Protection District (SRFPD)
Environmental Review
Following completion of the 30-day NOP public review period, the Town will incorporate relevant
information into the Draft EIR, including results of public scoping and technical studies.
Subsequently, the Draft EIR will be circulated for public review and comment for a 45-day public
review period.
The Town requests that any potential Responsible or Trustee Agency responding to this notice do so
in a manner consistent with CEQA Guidelines Section 15082(b). All parties that have submitted their
names and emails or mailing addresses will be notified throughout the CEQA review process.
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 13
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
A copy of the NOP (in full color) can be found on the Town ’s website:
https://danvilletowntalks.org/private-land-development.
If you wish to be placed on the mailing list or need additional information, please contact David
Crompton, Chief of Planning, Town of Danville Planning Division, at 925.314.3349 or
dcrompton@danville.ca.gov.
Potential Environmental Effects
The Draft EIR will evaluate if there are potentially significant environmental impacts associated with
approval and implementation of the proposed project. Consistent with the CEQA Guidelines
(Appendix G), the Draft EIR will analyze the reasonably foreseeable direct, indirect, and cumulative
effects of the proposed project on focused resources, including, but not limited to:
• Aesthetics, Light, and Glare • Hydrology and Water Quality
• Agricultural and Forestry Resources • Land Use and Planning
• Air Quality • Noise
• Biological Resources • Public Services
• Cultural Resources and Tribal Cultural Resources • Recreation
• Energy • Transportation
• Geology, Soils, and Seismicity • Utilities and Service Systems
• Greenhouse Gas Emissions • Wildfire
• Hazards and Hazardous Materials
Potentially Significant Environmental Issues
In preparation of the NOP and the Project Description, the Town has found that the following topical
areas may contain potentially significant environmental issues that will require further analysis in the
Draft EIR. These topical areas are as follows:
• Biological Resources–The proposed project site contains an environment with ephemeral
drainages and seasonal wetlands, which are protected by State and federal laws. Impacts to
these aquatic features could be potentially significant unless fully mitigated through the
implementation of mitigation measures or design features.
• Geology, Soils, and Seismicity–The proposed project site contains a documented history of
landslides and differing elevations and slopes. Impacts related to geology and soils could be
potentially significant unless fully mitigated through the implementation of mitigation
measures or design features.
• Transportation–The proposed project includes the extension of Como Way to serve the
proposed homes in addition to the existing homes along Como Way. Impacts related to traffic
could be potentially significant unless fully mitigated through the implementation of
mitigation measures of design features.
Town of Danville—Martin Hills Ranch Residential Project Notice of Preparation
FirstCarbon Solutions 14
Https://adecinnovations.sharepoint.com/sites/PublicationsSite/Shared Documents/Publications/Client (PN-JN)/5960/59600001/NOP/59600001 Danville Martin Hills Ranch NOP.docx
Effects Found not to be Significant
Unless specific comments are received during the NOP public comment period that indicate a
potential for the proposed project to result in a significant impact, the following issues will be
addressed in the Effects Found not to be Significant section of the Draft EIR.
•Mineral Resources—The 2030 General Plan Final EIR (2030 General Plan FEIR) identified that
no portion of the Town is designated by the California Department of Conservation as having
the potential to be a significant source of composite materials or industrial minerals.
Additionally, there are no known locally important mineral resources within the Town. As
such, the proposed project would have no impact related to mineral resources.
•Population and Housing–The proposed project would include 20 single-family homes and five
deed-restricted ADUs. As such, the proposed project would be expected to generate
approximately 70 residents. The current population of the Town is approximately 44,000
persons. The General Plan EIR projected an increase up to approximately 50,760 persons in
the year 2030. As such, the increase of approximately 70 persons estimated under the
proposed project would be well within the projected population increase of the General Plan
EIR as the current population of the Town is approximately 42,299 persons. Therefore, the
proposed project would not result in unplanned population growth. Additionally, the project
site is currently vacant, containing no residential structures. Therefore, the proposed project
would not displace existing persons or housing, and there would be no impacts related to
displacement of persons or housing.
NOTICE TO SURROUNDING PROPERlY OWNERS MAILED O I / \ J:/ W'VS BY 11M
"Small Town Atmosphere
Outstanding Quality of Life" NOTICE OF PREPARATION FOR AN ENVIRONMENTAL IMPACT REPORT AND NOTICE OF A PUBLIC SC OPING SESSION Project Title: Project Location/APN: Project Description: PUD 24-0002 and SD 9679 -Martin Hills Ranch Residential Project The site is located at the terminus of Borica Drive and Como Way. APN: 218-010-008 through 012 The Town of Danville has received an application to rezone the property from A-4; Agricultural Preserve District to a P-1; Planned Unit Development District. It also includes a 20-lot Major Subdivision request, and a Development Plan application for the architectural review of the proposed 20 new residences. The homes would be clustered into a hidden portion of the site, and the remaining portions of the 100 acre site would be designated as permanent open space. A Draft Environmental Impact Report (EIR) will be prepared to analyze any potential environmental impacts and associated mitigation measures. During the 30-day Notice of Preparation (NOP) public review period, people are encouraged to provide comments regarding the scope and content of the Draft EIR, a document which addresses potential environmental issues and mitigation measures. The Town will hold a Public Scoping Meeting to inform the public and interested agencies about the proposed project and solicit public comment on the scope of the environmental issues to be addressed in the Draft EIR as well as the range of alternatives to be evaluated.
500 LA GONDA WAY, DANVILLE, CALIFORNIA 94526
Administration Building Engineering & Planning
(925) 314-3388 (925) 314-3330 (925) 314-3310
Transportation
(925) 314-3310
Maintenance
(925) 314-3450
Police Parks and Recreation
(925) 314-3700 (925) 314-3400
ATTACHMENT B