STUDY SESSION MEMORANDUM 3.1
TO: Mayor and Town Council December 10, 2024
SUBJECT: Status Update for CIP B-560 Diablo Vista Park - Capital Maintenance
(Children’s Play Area) and CIP Project B-616 - Multi-Sport Skate Park
BACKGROUND
The Capital Improvement Program (CIP) includes projects to improve Diablo Vista Park.
CIP Project B-560 would replace and upgrade the existing children’s play area, and CIP
Project B-616 would construct a new multi-sport skatepark. In 2021, these two CIP
projects were combined to proceed with design and construction. This approach (“the
combined project”) was pursued because the children’s play area and skatepark sites are
located adjacent to one another, and it presented an opportunity to achieve economies of
scale and more favorable construction bids.
Initial Bid Process
After an extensive community engagement process, design work was completed for the
combined project, and construction bids were solicited in spring 2024. Two bids were
received and opened on June 4, 2024. The apparent low bid was for $2.92 million, with
the second bid at $4.79 million. The engineer’s cost estimate for the combined project was
$3.35 million. Town staff subsequently recommended awarding the construction contract
to the apparent low bidder at the July 2, 2024 Town Council meeting.
Prior to the award of the construction contract, the second bidder raised concerns
regarding various aspects of the project bid documents, and both bidders submitted bid
protests challenging aspects of each other’s bids. In light of concerns that were raised, the
Town Council subsequently acted to reject both construction bids and directed Town staff
to return with additional options to consider for moving forward.
At their August 13, 2024 Study Session, the Town Council considered additional options
including re-bidding the combined project or, alternately, separating the projects to allow
them to be bid separately. At the conclusion of the meeting, the Town Council opted to
proceed with revising the engineering design and bid documents to allow the children’s
play area and the new multi-sport skatepark to potentially be bid and constructed
separately. On September 3, 2024, the Town Council approved an amended professional
services agreement with the project consultants to allow this to occur.
Diablo Vista Park 2 December 10, 2024
DISCUSSION
The revised plans, separate bid packages and revised engineer’s estimates for the two
projects have now been completed to allow for further consideration of how to proceed.
Timing of construction is critical for two reasons. First, the age and condition of the
existing children’s play area continue to warrant prompt attention. Second, ARPA funds
committed to the project include stringent performance deadlines.
Engineer’s Cost Estimate
Base Project Additional Bid
Alternates
Total
CIP B-560 - Children’s
Play Area
$1,925,250 $243,995
(shade structure, fitness
equipment, boulders)
$2,169,245
CIP B-616 - Multi-Sport
Skate Park
$1,787,261 $363,120
(lighting and boulders)
$2,150,381
$3,712,511 $607,115 $4,319,626
A total of $3,301,608 is available for construction, including $959,628 in CIP Project B-560,
and $2,341,980 in CIP Project B-616. The combined updated engineer’s estimates for the
base project alternates exceed the available construction budget by $410,903.
Options to Proceed
The Town is now prepared to move forward with soliciting construction bids as the next
step in this process. Bids may be solicited for either or both projects. Further
determination regarding whether and how to proceed with construction can occur once
bids are received and opened. At that time, further consideration will be required to
determine:
• Funding - Adequacy of project funding available to fund both projects and
potential additional bid alternates.
• Construction Timing - The current project timeline could allow construction to
begin as soon as spring 2025. Bidding both projects potentially allows one
contractor to successfully bid both projects. Should two low bidders emerge from
the process (one for each of the two projects) it may be preferable to stagger
construction to avoid having both projects underway simultaneously, along with
related staging requirements for two separate contractors.
Diablo Vista Park 3 December 10, 2024
RECOMMENDATION
Review and consider the options and information presented and provide further
direction to staff regarding how to proceed.
Prepared by:
Bob Russell
Landscape Architect
Reviewed By:
Joseph A. Calabrigo
Town Manager
Attachments: A – Skatepark and Play Area Site Plan
B – Phased Skatepark and Play Area Site Plan
C – Play Area Site Plan
D – Photos – Existing Play Area
E – Concept Plan Renderings
A
T
T
A
C
H
M
E
N
T
A
A
T
T
A
C
H
M
E
N
T
B
ATTACHMENT C
2-5 yrs. Play area – deterioration of safety surfacing and wood elements
5-12 yrs. Play area - deterioration of wood elements and removed play feature