ADMINISTRATIVE STAFF REPORT 5.3
TO: Mayor and Town Council November 6, 2024
SUBJECT: Resolution No. 74-2024, awarding a construction contract for the Camino
Tassajara Pkwy/Sycamore Valley Road Sound Wall Maintenance Project,
CIP No. A-513F
BACKGROUND
The masonry sound walls along Camino Tassajara Pkwy and Sycamore Valley Road were
originally built when the area developed about 35 years ago, and now require
maintenance to address problems reported by adjacent residents. Project No. A-513F was
included in the Capital Improvement Program (CIP) to provide ongoing maintenance for
these masonry walls. The work consists of 13 project sites along Camino Tassajara Pkwy
and Sycamore Valley Road between Brookside Drive and Liverpool Street.
DISCUSSION
Three (3) bids were received and opened on October 22, 2024. The lowest responsive
bidder was Cowan & Thompson Construction Inc. of Martinez, California at $230,662.00.
Bid results are summarized in Attachment C.
The work is scheduled to begin this winter, assuming the weather is favorable.
This project is considered maintenance and repair work, and is therefore categorically
exempt from the requirements of the California Environmental Quality Act (CEQA)
according to Guidelines Section 15301 (Class 1).
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public. Adjacent property
owners will be notified in advance of the construction schedule.
FISCAL IMPACT
The low bid amount is $230,662, plus a 20% contingency of $47,000, results in a total
construction budget of $277,662. Sufficient funds to cover the construction and
contingency are contained in Camino Tassajara Pkwy/Sycamore Valley Road Sound
Award of Contract 2 November 6, 2024
Soundwall Maintenance
CIP No. A-513F
Wall Maintenance Project, CIP No. A-513, (Attachment B).
RECOMMENDATION
Adopt Resolution No. 74-2024, awarding a construction contract the Camino Tassajara
Pkwy/Sycamore Valley Road Sound Wall Maintenance Project, CIP No. A-513F.
Prepared by:
Nader Salama
Senior Civil Engineer
Reviewed by:
Diane J. Friedmann
Development Services Director
Attachments: A - Resolution No. 74-2024
B - CIP Page No. A-513
C – Bid Results Summary
RESOLUTION NO. 74-2024
AWARDING A CONSTRUCTION CONTRACT FOR THE CAMINO TASSAJARA
PKWY/SYCAMORE VALLEY ROAD SOUND WALL MAINTENANCE PROJECT,
CIP NO. A-513F
WHEREAS, the Danville Town Council has appropriated funding in the Capital
Improvement Program for the Camino Tassajara Pkwy/Sycamore Valley Road Sound
Wall Maintenance Project, CIP No. A-513F in the 2024/25 Capital Improvement Program;
and
WHEREAS, additional sound wall repairs were added to the project, increasing the costs
above the CIP estimate; and
WHEREAS, the plans and specifications for the subject project have been reviewed and
approved by the City Engineer; and
WHEREAS, this project is categorically exempt from the requirements of the California
Environmental Quality Act, Section 15301, Class 1; and
WHEREAS, the City Clerk of this Town did, in open session on the 22nd day of October,
2024, publicly open and read aloud the sealed bids received as required by law; and
WHEREAS, the lowest responsive bidder is Cowan & Thompson Construction Inc. of
Martinez, California, and the City Engineer has recommended awarding a contract for
the project to said contractor; now, therefore, be it
RESOLVED, by the Danville Town Council, that the Town award the construction
contract for the Camino Tassajara Pkwy/Sycamore Valley Road Sound Wall
Maintenance Project, CIP No. A-513F to Cowan & Thompson Construction Inc. of
Martinez, California; and, be it further
RESOLVED, by the Danville Town Council, that the Town Manager be and hereby is
authorized to execute, on behalf of the Town, a written contract with Cowan & Thompson
Construction Inc. of Martinez for $230,662 and authorize use of a 20% construction
contingency of $47,000 for a total construction budget of $277,662 for work in connection
therewith, and the City Clerk is hereby directed to attest same and affix thereto the official
seal of the Town.
Docusign Envelope ID: A160AC25-D684-4FE1-88C5-FC54457DEF43
ATTACHMENT A
PAGE 2 OF RESOLUTION NO. 74-2024
APPROVED by the Danville Town Council at a regular meeting on November 6, 2024,
by the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
_____________________________________
MAYOR
APPROVED AS TO FORM: ATTEST:
________________________________ ______________________________________
CITY ATTORNEY CITY CLERK
Docusign Envelope ID: A160AC25-D684-4FE1-88C5-FC54457DEF43
Town of Danville
www.danville.ca.gov • CIP 38
Projects
CAMINO TASSAJARA PKWY/SYCAMORE VALLEY RD SOUND WALL MAINT.
CIP No:A-513 STATUS:In Design PRIORITY:2/3 Ongoing PROJECT MANAGER:NNS
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
Increased funding FY 25-29.
RATIONALE FOR PROPOSED PROJECT:
Ongoing maintenance is needed for the 25 year old infrastructure.EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:150
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
This project has been modified from the previous year.
PROJECT APPROPRIATION AND FUNDING
Establish an ongoing maintenance program for the sound walls maintained
by the Town, generally along Camino Tassajara Parkway and Sycamore
Valley Road.
Estimates of future wall maintenance costs based on last year indicated
additional funding is needed to maintain current quality standards and
repair failures.
5/23/2024PRINTED ON:
GREEN PROJECT:No
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalExpenditure Category
Design/Plan Review $0 $0 $0 $0$0 $0$0
Construction $200,000 $200,000 $200,000 $200,000$915,420 $1,815,420$100,000
Inspection & Admin.$0 $0 $0 $0$17,305 $17,305$0
$932,725 $100,000 $200,000 $200,000 $200,000 $200,000 $1,832,725Total Cost Estimate:
$576,982Total Expenditure: Unexpended: $355,743 on 05-01-2024
2024/25Prior Years 2025/26 2026/27 2027/28 2028/29 TotalFunding Source(s)
CIP Gen Purpose Rev $807,725 $100,000 $200,000 $200,000 $200,000 $1,707,725$200,000
LLAD Zone B $125,000 $0 $0 $0 $0 $125,000$0
$932,725 $100,000 $200,000 $200,000 $200,000 $200,000 $1,832,725Total Funding:
www.danville.ca.govCIP43ATTACHMENT B
PROJECT: Camino Tassajara/Sycamore Valley Road
Sound Wall Maintenance Project, Contract
No. A-513F
BID OPENING: October 22, 2024, at 2:00 p.m. PST
Please direct all questions regarding this bid opening to:
Project Manager: Nader Salama, Senior Civil Engineering, (925) 314-3348
nsalama@danville.ca.gov
Addendums: None
BID RESULTS SUMMARY
CONTRACTOR BID AMOUNT
*Cowan and Thompson $230,662.00
E.E. Gilbert Construction $237,340.00
ELLA $369,576.00
$
$
$
$
$
$
*Lowest Responsive Bid