HomeMy WebLinkAbout022123-09.4 ADMINISTRATIVE STAFF REPORT 9.4
TO: Mayor and Town Council February 21, 2023
SUBJECT: Resolution No. 16-2023, authorizing an Emergency Storm Drain Culvert
Replacement contract pursuant to California Public Contract Code
Sections 20168 and 22050 and appropriating additional funding for
Town-wide Storm Drain System Management, CIP No. A-330
BACKGROUND
The Town of Danville continues to operate under the local state of emergency declared
on January 10, 2023 as a result of several atmospheric rivers that hit the San Francisco
Bay Area starting on December 31, 2022 and continued through January 2023.
These storms caused damage to Town infrastructure including a 12-foot diameter
drainage culvert under Diablo Road, immediately east of Alameda Diablo. Once the
storms subsided, a detailed inspection of the drainage culvert concluded that the
structural integrity of the culvert has been compromised by these winter storms.
Consequently, it is recommended that an emergency project be undertaken to replace
the culvert as soon as practicable.
DISCUSSION
The emergency culvert replacement would require closure of Diablo Road, between
Alameda Diablo and Avenida Nuevo. The temporary road closure would result in the
shortest project duration and cost efficiency. The project duration is anticipated to be
approximately three weeks and is expected to commence in late March 2023, aligning
with the spring break schedules of the local public and private schools to the greatest
degree possible.
Informal bids were received during the week of February 6, 2023. The lowest
responsive bidder was Teichert Construction of Pleasanton, California at $1,364,000.
Bid results are summarized in Attachment C. Construction is expected to begin in late
March 2023.
Emergency projects are exempt from the requirements of the California Environmental
Quality Act (CEQA) according to California Public Resources Code Section 21080(b)(2)
and Guidelines Section 15269.
Authorizing Emergency Culvert 2 February 21, 2023
Replacement on Diablo Road
CIP No. A-330
Public Contract Code 20168 states that in case of an emergency, the Town Council may
pass a resolution by a four-fifths vote that the public interest and necessity demand the
immediate expenditure of public money to safeguard life, health, or property. Upon
adoption of the resolution, the Town may expend any sum required in the emergency
without complying with the code. If a notice for bids to let contracts is not given, the
Town Council shall comply with Public Contract Code Section 22050, which provides
that, with a four-fifths vote, a finding may be made, based on substantial evidence set
forth in the minutes of its meeting, that the emergency will not permit a delay resulting
from a competitive solicitation for bids, and that the action is necessary to respond to
the emergency. The attached resolution contains such findings.
COMMUNITY OUTREACH
The community outreach effort associated with this emergency project would include
(but not limited to) coordination with local public agency partners, such as Contra
Costa County District 2 Supervisor’s Office, Contra Costa County Public Works
Department, San Ramon Valley Unified School District, San Ramon Valley Fire
Projection District and Mount Diablo State Park.
In addition, all residential addresses that take access from Diablo Road (east of Green
Valley Road) or Blackhawk Road will be notified by a direct mail postcard. All nearby
Homeowners Associations would also receive a mailed notification.
Changeable message signs (electronic reader boards) would be placed in advance of all
approaches to Diablo and Blackhawk Roads. Furthermore, static printed notification
signs would be placed at the entrance to all neighborhoods along the roadway corridor.
The Town would also issue a press release, post information on all Town sites and
social media platforms, and distribute information on both the County District 2
newsletter as well as the Danville Area Chamber of Commerce newsletter. Lastly, a
project page has been developed (www.DanvilleTownTalks.org/DiabloCulvert) to
allow residents to get up-to-date information about detour routes, project updates, and
local resident access.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public. Adjacent property
owners will be notified in advance of the construction schedule.
FISCAL IMPACT
The low bid amount of $1,364,000 plus a 30% contingency of $410,000 results in a total
construction budget of $1,774,000. An appropriation of $1,774,000 will be required from
Authorizing Emergency Culvert 3 February 21, 2023
Replacement on Diablo Road
CIP No. A-330
CIP General Purpose Revenue in order to fully fund the project.
RECOMMENDATION
Adopt Resolution No. 16-2023, authorizing an Emergency Storm Drain Culvert
Replacement contract pursuant to California Public Contract Code Sections 20168
and 22050 and appropriating additional funding for Town-wide Storm Drain
System Management, CIP No. A-330.
Prepared by:
Steven Jones, P.E.
City Engineer
Reviewed by:
Tai J. Williams
Assistant Town Manager
Attachments: A – Resolution No. 16-2023
B – CIP Pages No. A-330
C – Bid Results Summary
RESOLUTION NO. 16-2023
AUTHORIZING AN EMERGENCY STORM DRAIN CULVERT
REPLACEMENT CONTRACT PURSUANT TO CALIFORNIA PUBLIC
CONTRACT CODE SECTIONS 20168 AND 22050 AND APPROPRIATING
ADDITIONAL FUNDING FOR TOWN-WIDE STORM DRAIN SYSTEM
MANAGEMENT, CIP NO. A-330
WHEREAS, a series of major storm events that started on December 31, 2022, and
continued through January 2023 caused the initiation of emergency repairs to Town
streets and facilities; and
WHEREAS, the Town of Danville continues to operate under the local state of
emergency declared on January 10, 2023; and
WHEREAS, California Public Contract Code Section 20168 states that in case of an
emergency, the Town Council may pass a resolution by a four-fifths vote that the public
interest and necessity demand the immediate expenditure of public money to safeguard
life, health, or property; and
WHEREAS, California Public Contract Code Section 22050 states that a finding shall be
made, based on substantial evidence set forth in the minutes of its meeting, that the
emergency will not permit a delay resulting from a competitive solicitation for bids, and
that the action is necessary to respond to the emergency; and
WHEREAS, said emergency work is exempt from the requirements of the California
Environmental Quality Act according to California Public Resources Code Section
21080(b)(2) and Guidelines Section 15269; and
WHEREAS, the Danville Town Council has appropriated funding in the Capital
Improvement Program for the Town-wide Storm Drain System Management, CIP No.
A-330 in the 2022/23 Capital Improvement Program; and
WHEREAS, the Town solicited informal bids from contractors because the formal
competitive bidding process would have delayed immediate action; and
WHEREAS, the lowest responsive bidder is Teichert Constrction of Pleasanton,
California, at $1,364,000 and the City Engineer has recommended awarding a
construction contract for the project to said contractor; now, therefore, be it
RESOLVED, that the Danville Town Council finds, based on substantial evidence, that
the replacement of the storm drain culvert on Diablo Road is an emergency that would
not permit a delay resulting from a competitive solicitation of bids, and that immediate
action is necessary to respond to said emergency in conformance with California Public
Contract Code §22050; and, be it further
DocuSign Envelope ID: 5000552C-2C43-46CC-B1EE-A91A4C0937EB
ATTACHMENT A
RESOLVED, by the Danville Town Council that it was in the public interest to expend
public money to safeguard life, health, and/or property in conformance with California
Public Contract Code §20168; and, be it further
RESOLVED, by the Danville Town Council, that $1,774,000, in CIP General Purpose
Revenue be appropriated in Fiscal Year 2022/23 for CIP No. A-330 to fund construction
of the project; and, be it further
RESOLVED, by the Danville Town Council, that the Town award a construction
contract for the Emergency Diablo Road Culvert Replacement as part of Town-wide
Storm Drain System Management, CIP No. A-330 to Teichert Constrction of Pleasanton,
California; and, be it further
RESOLVED, by the Danville Town Council, that the Town Manager be and hereby is
authorized to execute, on behalf of the Town, a written contract with Teichert
Construction of Pleasanton, California for $1,364,000 and authorize use of a 30%
contingency amount of $410,000 for a total construction budget $1,774,000 for work in
connection therewith, and the City Clerk is hereby directed to attest same and affix
thereto the official seal of the Town; and, be it further
RESOLVED, that staff shall within five (5) days of the adoption of this resolution,
transmit an Extract of Public Works contract award to the Department of Industrial
Relations, Division of Apprenticeship Standards, P.O. Box 420603, San Francisco, CA
94142. (Note: Should a finding of any discrepancy regarding this ratio of apprentices to
journeymen be made, the Town shall notify the Division of Apprenticeship Standards
of such findings.)
APPROVED by the Danville Town Council at a regular meeting on February 21, 2023,
by the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
MAYOR
APPROVED AS TO FORM: ATTEST:
CITY ATTORNEY CITY CLERK
DocuSign Envelope ID: 5000552C-2C43-46CC-B1EE-A91A4C0937EB
www.danville.ca.govCIP34
72:1:,'(67250'5$,16<67(00$1$*(0(17
&,31R 67$786(M#DRHFM 35,25,7<.MFNHMF 352-(&70$1$*(52)
352-(&7'(6&5,37,21$1'/2&$7,21
'(6&5,37,212)02',),&$7,216
$GGHGIXQGLQJIRU
5$7,21$/()25352326('352-(&7
0DLQWHQDQFHRIWKHH[LVWLQJVWRUPGUDLQV\VWHPLVQHHGHGRQDQ
RQJRLQJEDVLV
(;3(&7(',03$&72123(5$7,1*%8'*(7$GGLWLRQDOZRUNHUKRXUVUHTXLUHGWRPDLQWDLQSHU\HDU
$GGLWLRQDO7RZQGLUHFWRSHUDWLQJFRVWVSHU\HDU
352-(&7&267(67,0$7(
7KLVSURMHFWKDVEHHQPRGLILHGIURPWKHSUHYLRXV\HDU
352-(&7$335235,$7,21$1')81',1*
7KLVSURMHFWSURYLGHVIRURQJRLQJFDSLWDOUHSODFHPHQWDQGPDLQWHQDQFHRI
WKH7RZQZLGHGUDLQDJHV\VWHP
2QJRLQJDQGDVQHHGHGZRUNLQFOXGHV
&OHDQLQJDQGGHVLOWLQJGLWFKHVDQGSLSHVDVQHHGHG
5HSDLUEURNHQSLSHVFDWFKEDVLQVDQGFRQFUHWHOLQHGGLWFKHV
5HSDLUEURNHQFXUEVJXWWHUVDQGYDOOH\JXWWHUV
,QVWDOODQGPDLQWDLQWUDVKUHPRYDOGHYLFHVLQWKH'RZQWRZQDUHD
5HSDLURIIDLOHGRXWIDOOSLSHLQWR6DQ5DPRQ&UHHNDW1RUWK
+DUW]$YHQXH'DQYLOOH%RXOHYDUG&RPSOHWH
3HUIRUPDFRQGLWLRQDVVHVVPHQWDQGGHYHORSD6WRUP
'UDLQDJH0DVWHU3ODQWRLGHQWLI\SULRULWL]HDQGHVWLPDWHWKH
FDSLWDOLPSURYHPHQWFRVWVRIIXWXUHSURMHFWV
)XWXUH3URMHFWV9LVWD*UDQGH'UDLQDJH,PSURYHPHQWV
(OVLH'ULYHDQG/RPLWDV'ULYH6WRUP'UDLQ5HSODFHPHQW
*UHHQEURRN'ULYH6WRUP'UDLQ5HSDLU
35,17('21
*5((1352-(&78DR
3ULRU<HDUV 7RWDO([SHQGLWXUH&DWHJRU\
'HVLJQ3ODQ5HYLHZ
&RQVWUXFWLRQ
,QVSHFWLRQ $GPLQ
7RWDO&RVW(VWLPDWH
7RWDO([SHQGLWXUH8QH[SHQGHGRQ
3ULRU<HDUV 7RWDO)XQGLQJ6RXUFHV
$53$
&,3*HQ3XUSRVH5HY
&OHDQZDWHU3URJUDP
'HYHORSHU&RQWULEXWLRQ
7RWDO)XQGLQJ
Projects
ATTACHMENT B
INFORMAL BID RESULTS SUMMARY
Emergency Culvert Replacement on Diablo Road
Week of February 6, 2023
Teichert Construction $1,364,000
Goodfellow Bros. $1,596,322
McGuire and Hester Declined to bid
ATTACHMENT C