Summary & Status
TWO-PART CONSTRUCTION
Easterly section underway by the developer, as part of the Magee Preserve subdivision improvements
Westerly section will be constructed by the Town in 2023, connecting to Barbara Haile Trail (existing)
2
Athenian
SchoolGreen Valley
Elementary
School Diablo Road
Developer
constructed
trail segment
(0.7 miles)
Town constructed trail
segment (0.9 miles)
Existing Diablo Road
Trail (0.5 miles)
EASTERN SEGMENT
Developer constructed
trail segment
WESTERN SEGMENT (PART 1)
Town constructed trail to follow
existing EVA alignment
Trail Crossing -
“HAWK” Signal
DIABLO ROAD TRAIL ALIGNMENT & CROSSING
LOCATION MAP
Avenida
Nueva
4
PROJECT STATUS
& NEXT STEPS
•Summer 2020: In-house preliminary
design; grant submittals
•Fall 2020: Project area specific
topographic survey (validate preliminary
design)
•2021:Environmental assessment and
regulatory permitting process
•Spring 2022: Diablo Road/ Fairway Drive
crossing treatment design began
•Oct/Nov 2022: Mitigated Negative
Declaration (“MND”) of Environmental
Impacts (45-day comment period)
•December 20,2022: Town Council
adoption of MND and approval of
alignment
•Winter 2023:Final Design
•Summer/Fall 2023:Bid process and
Construction begins