HomeMy WebLinkAbout073-2022DocuSign Envelope ID: FD6F369B-3432-4C18-9EF9-C9010BODBF01
RESOLUTION NO. 73-2022
APPROPRIATING FUNDS FOR THE OAK HILL PARK PLAYGROUND
REPLACEMENT PROJECT, CIP NO. B-544
WHEREAS, the Danville Town Council has approved and appropriated funding for CIP
No. B-544 Oak Hill Park Capital Maintenance in the 2022/23 Capital Improvement
Program; and
WHEREAS, the Danville Town Council adopted Resolution No. 60-2022, awarding a
construction contract to Ross Recreation Equipment, Inc. for the Oak Hill Park
Playground Replacement Project; and
WHEREAS, a total construction budget of $1,025,000 is required to complete the project;
and
WHEREAS, an unexpended amount of $700,000 in funds previously appropriated by the
Town Council is available to partially fund the construction contract; and
WHEREAS, an appropriation of $325,000 from the Park Dedication Impact Fund to CIP
No. B-544 is required to fully fund the project; now, therefore, be it
RESOLVED, by the Danville Town Council, that $325,000 from the Park Dedication
Impact Fund be appropriated in fiscal year 2022/23 for CIP No. B-544 to fully fund the
project.
APPROVED by the Danville Town Council at a regular meeting on September 6, 2022,
by the following vote:
AYES: Arnerich, Fong, Morgan, Stepper, Storer
NOES: None
ABSTAINED: None
ABSENT: None
DocuSig�:
7nci FRRn7nnaa75
MAYOR
APPROVED AS TO FORM: ATTEST:
r--DocuSigned by:
g44g4c44 R. E4(441
\—pac `A AnznRFARF
i_DocuSi ned by:
71735A3F04C942F
CITY ATTORNEY CITY CLERK