TO: Mayor and Town Council May 17, 2022
SUBJECT: Resolution No. 40-2022, awarding a construction contract and
appropriating additional funding for the Demolition of Buildings
Located at 219 Weber Lane and 282 Front Street Project, CIP No. B-427 &
B-629
BACKGROUND
The Town’s Capital Improvement Program includes the Oak Hill Master Plan – Phase 2
and 282 Front Street – Arts District Maker Space, CIP’s No. B-427 & B-629 respectively.
Demolition of buildings located at 219 Weber Lane and 282 Front Street are included in
these projects.
This project includes demolition of the existing structures located at 282 Front Street
(single-story house and single-story garage) and the “Weber House” (single-story house,
single-story garage, and single-story barn) located at 219 Weber Lane. Work also includes
capping of existing utilities, removal of slab foundations, trucking, and disposal of all
materials.
DISCUSSION
Seven bids were received and opened on April 26, 2022. The lowest responsive bid was
submitted by Unlimited Environmental, Inc. of Long Beach, California, with a bid of
$75,000. Bid results are summarized in Attachment C. The Engineer’s estimate was
$90,000.
The work is scheduled to begin in summer 2022 and be completed later in 2022, weather
permitting.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public. Before construction
begins, residents and businesses within close proximity to the project will be notified by
the contractor in writing. In addition, project identification signs will be posted.
FISCAL IMPACT
The low bid amount of $75,000, plus a 20% contingency amount of $15,000, yields a total
Award of Construction Contract 2 May 17, 2022
Demolition of Buildings at 219 Weber Lane
and 282 Front St, CIP No. B-427 & B-629
construction budget of $90,000. An appropriation in the amount of $90,000 from Park
Facilities Fund is needed to fully fund the project.
RECOMMENDATION
Adopt Resolution No. 40-2022, awarding a construction contract and appropriating
additional funding for the Demolition of Buildings Located at 219 Weber Lane and 282
Front Street Project, CIP No. B-427 & B-629.
Prepared by:
Steven Jones, P.E.
City Engineer
Reviewed by:
Tai J. Williams
Assistant Town Manager
Attachments: A – Resolution No. 40-2022
B – CIP Pages No. B-427 & B-629
C – Bid Results Summary
RESOLUTION NO. 40-2022
AWARDING A CONSTRUCTION CONTRACT AND APPROPRIATING
ADDITIONAL FUNDING FOR THE DEMOLITION OF BUILDINGS LOCATED
AT 219 WEBER LANE AND 282 FRONT STREET PROJECT, CIP NO. B-427 & B-629
WHEREAS, the Danville Town Council has previously approved including projects in
the Capital Improvement Program for the Oak Hill Master Plan – Phase 2 and 282 Front
Street – Arts District Maker Space, CIP’s No. B-427 & B-629 respectively; and
WHEREAS, the projects include demolition of buildings located at 219 Weber Lane and
282 Front Street; and
WHEREAS, bids were solicited from contractors for the project; and
WHEREAS, the City Clerk of this Town did, in open session on the 26th day of April,
2022, publicly open and read aloud the sealed bids received as required by law; and
WHEREAS, of the seven bids received, the lowest responsive bid was submitted by
Unlimited Environmental, Inc. of Long Beach, California, and the City Engineer
recommends awarding a construction contract for the project to said contractor; now,
therefore, be it
RESOLVED, by the Danville Town Council, that $70,000 in Park Facility Funds be
appropriated in fiscal year 2021/22 for CIP No. B-427 to fund construction of the project;
and, be it further
RESOLVED, by the Danville Town Council, that $20,000 in Park Facility Funds be
appropriated in fiscal year 2021/22 for CIP No. B-629 to fund construction of the project;
and, be it further
RESOLVED, by the Danville Town Council, that the Town award a construction contract
for the demolition of buildings located at 219 Weber Lane and 282 Front Street, CIP No.
B-427 and B-629, to Unlimited Environmental, Inc. of Long Beach, California; and, be it
further
RESOLVED, by the Danville Town Council, that the Town Manager be and hereby is
authorized to execute, on behalf of the Town, a written contract with Unlimited
Environmental, Inc. of Long Beach, California for $75,000 and authorize use of a 20%
contingency not-to-exceed $15,000, for a total construction budget of $90,000, for work in
connection therewith, and the City Clerk is hereby directed to attest same and affix
thereto the official seal of the Town; and, be it further
RESOLVED, that staff shall within five (5) days of the adoption of this resolution,
transmit an Extract of Public Works contract award to the Department of Industrial
DocuSign Envelope ID: 560C48E8-1FEF-4092-B140-81CE5569BE59
ATTACHMENT A
Relations, Division of Apprenticeship Standards, P.O. Box 420603, San Francisco, CA
94142. (Note: Should a finding of any discrepancy regarding this ratio of apprentices to
journeymen be made, the Town shall notify the Division of Apprenticeship Standards of
such findings.)
APPROVED by the Danville Town Council at a regular meeting on May 17, 2022, by the
following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
MAYOR
APPROVED AS TO FORM: ATTEST:
CITY ATTORNEY CITY CLERK
DocuSign Envelope ID: 560C48E8-1FEF-4092-B140-81CE5569BE59
www.danville.ca.govCIP63
Projects
OAK HILL MASTER PLAN - PHASE 2
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
RATIONALE FOR PROPOSED PROJECT:
Help meet growing community needs for active recreational facilities.
EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:0
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
This project is currently unfunded.
PROJECT APPROPRIATION AND FUNDING
UNFUNDED
Evaluate the development potential of the undeveloped (southern) portion of Oak Hill Park to meet unmet community needs.
Development of the adjacent Weber property provides additional access to the property.
Project includes demolition of the existing Weber House (located on the Town-owned 3.66 acre parcel adjacent to the park) that was dedicated to the Town as part of the Weber/Davidon development in order to improve ingress to the south end of the park.
Based upon other planning/design/construction priorities for Town parks and community facilities, this project has been deferred.
6/4/2021PRINTED ON:
CIP No:B-427 STATUS:Adopted PRIORITY:5 PROJECT MANAGER:HRPGREEN PROJECT:Yes
2021/22Prior Years 2022/23 2023/24 2024/25 2025/26 TotalExpenditure Category
Design/Plan Review $0 $0 $0 $0$0 $0$0
Construction $0 $0 $0 $0$0 $0$0
Inspection & Admin.$0 $0 $0 $0$0 $0$0
$0 $0 $0 $0 $0 $0 $0Total Cost Estimate:$0Total Expenditure: Unexpended: $0 on 6-03-2021
2021/22Prior Years 2022/23 2023/24 2024/25 2025/26 TotalFunding Source(s)
Park Facilities $0 $0 $0 $0 $0 $0$0
Unfunded-87 $0 $0 $0 $0 $0 $0$0
$0 $0 $0 $0 $0 $0 $0Total Funding:
www.danville.ca.govCIP61
Projects
ATTACHMENT B
www.danville.ca.govCIP88
Projects
282 FRONT STREET - ARTS DISTRICT MAKER SPACE
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
RATIONALE FOR PROPOSED PROJECT:EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:0
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
This project is currently unfunded.
PROJECT APPROPRIATION AND FUNDING
UNFUNDED
The Parks, Recreation and Arts Commission recommends this an a high priority parks project. This project is identified in the Parks, Recreation and Arts Strategic Plan as an important to the Parks, Recreation and Arts System.
This project includes a comprehensive set of improvements, activities and arts program strategies to activate the Town Green and Arts District on Front Street. The Front Street property was specifically identified in the Town Green and Arts District Master Plan. The project includes a new building to become a maker space with restrooms, outdoor area including shade trellises, community tables and other seating.
Purchase of Property $600,000Design and Construction of Maker Space
6/4/2021PRINTED ON:
CIP No:B-629 STATUS:Adopted PRIORITY:4 PROJECT MANAGER:HRPGREEN PROJECT:No
2021/22Prior Years 2022/23 2023/24 2024/25 2025/26 TotalExpenditure Category
Design/Plan Review $600,000 $0 $0 $0$0 $600,000$0
$0 $0 $600,000 $0 $0 $0 $600,000Total Cost Estimate:Total Expenditure:Not Available
2021/22Prior Years 2022/23 2023/24 2024/25 2025/26 TotalFunding Source(s)
Unfunded-87 $0 $0 $0 $0 $0 $600,000$600,000
$0 $0 $600,000 $0 $0 $0 $600,000Total Funding:
www.danville.ca.govCIP86
Projects
PROJECT: Demolition of Buildings located at 219 Weber
Lane “Weber House” and 282 Front St.
Contract No. CIP B-427 & B-629
BID OPENING: April 26, 2022, at time 2:00 p.m. PST
Please direct all questions regarding this bid opening to
Steven Jones, City Engineer, (925) 314-3339
SJones@danville.ca.gov
OFFICIAL BID RESULTS SUMMARY
CONTRACTOR BID AMOUNT
*Unlimited Environmental, Inc.$75,000.00
Garrison Demolition and Engineering $78,000.00
Sierra Excavating $107,636.00
Demolition Services and Grading $108,230.00
A-1 Construction $118,000.00
Central Valley Environmental $131,648.00
Dave McNabb Construction $143,500.00
*Lowest Responsive Bid