Loading...
HomeMy WebLinkAbout101320 Diablo Trail Alignment Presentation1 Status Update: Diablo Road Trail CIP Project C-055 Danville Town Council Study Session October 13, 2020 2 2 2018 Feasibility Analysis Assessment of Three Options: 1.Road Crossings 2.Trail Alignment 3.Drainage Crossings Estimate of Costs & Evaluation of Challenges 3 Existing EVA Diablo Road Trail: Feasibility Analysis Summary 4 5 •In-house preliminary design began April 2020 •Alternative alignment with less terrain obstacles, lower cost, ADA compliant •New topographic survey (Fall 2020) •Diablo Rd/Fairway Dr crossing design (Fall-Winter 2020) •Final design (Winter 2021) •Environmental assessment to assess impacts, arborist report, assist with permitting (9-12 months) Preliminary Design –Alignment Alternative Diablo Road Trail Update: Current Status 6 TRAIL TYPICAL SECTION TOWN OF DANVILLE DIABLO ROAD TRAIL PROJECT PLAN SCALE: 1" = 100' PROJECT VICINITY MAP NOT TO SCALE PROJ E C T L I M I T S SCALE:1" = 100' 4002001000 FEET Alternative Alignment (Full Trail Segment)Alameda Diablo Fairway Drive Tank Access Road 7 TRAIL TYPICAL SECTION TOWN OF DANVILLE DIABLO ROAD TRAIL PROJECT PLAN SCALE: 1" = 100' PROJECT VICINITY MAP NOT TO SCALE PROJ E C T L I M I T S SCALE:1" = 100' 4002001000 FEET Alternative Alignment 8 TRAIL TYPICAL SECTION TOWN OF DANVILLE DIABLO ROAD TRAIL PROJECT PLAN SCALE: 1" = 100' PROJECT VICINITY MAP NOT TO SCALE PRO J E C T L I M I T S SCALE:1" = 100' 4002001000 FEET Alternative Alignment Alameda Diablo Fairway Dr Calle Arroyo 9 10 •8-foot wide paved pathway •Alignment from Fairway Drive to Alameda Diablo –parallel to Diablo Road on south side, @1,000 feet long •Re -establish creek bank with Mechanically Stabilized Earth (“MSE”) walls – limited environmental impact and provides required width for pathway •Roadway Crossing –Fairway Drive/Diablo Road intersection Culvert crossing –east of Diablo Rd/Alameda Diablo intersection •4 to 5-foot separation of pathway from roadway with barrier options (guardrail/split rail fencing -TBD) •ADA compliant •Total Trail Length = 4,500 LF Design Elements Diablo Road Trail: Alternative Alignment 11 11 •$4M project, @$2M funding gap •2020 Grant Submittals (for Construction phase) -Active Transportation Program (ATP), Cycle 5 -Caltrans Highway Safety Improvement Program (HSIP), Cycle 10 Funding Diablo Road Trail: Funding & Next Steps Next Steps •Topographic Survey (Fall 2020) •Final Design (Winter 2021) •Environmental Clearance/Permitting (2021) •Grant Award Notice (Spring 2021) •Construction (2022-23) 12 Diablo Road Trail: Status Update Questions?