HomeMy WebLinkAbout020420-05.3 ADMINISTRATIVE STAFF REPORT 5.3
TO: Mayor and Town Council February 4, 2020
SUBJECT: Resolution No. 5-2020, authorizing a Professional Services Agreement to
develop and prepare a Town-wide Bicycle Master Plan, CIP No. C-609
BACKGROUND
The Town’s 2019/20 Capital Improvement Program (“CIP”) includes Project C-609 –
Town-wide Bicycle Master Plan (“BMP”). Currently, planning and development of
Danville’s bicycle facilities are guided by the Contra Costa Countywide Bicycle and
Pedestrian Plan and the goals and policies defined in the Town’s 2030 General Plan.
While these documents provide policy-level guidance, the development of a BMP is
intended to create a comprehensive long-range plan focused on bicycle policies and
infrastructure improvements within the Town.
DISCUSSION
On November 21, 2019, a Request for Proposal (“RFP”) for the BMP was posted to the
Town’s website. In response, two (2) proposals were received from local consulting
firms. The Town carefully reviewed and ranked the two submitted proposals. Alta
Planning + Design Inc. of Oakland, CA received the highest ranking and was found to be
the most qualified consultant for the project.
PUBLIC CONTACT
Posting of the meeting agenda serves as notice to the general public.
FISCAL IMPACT
The amount of the contract to develop and prepare a Town-wide Bicycle Master Plan is
$75,000. Sufficient funds have been appropriated in the Town’s adopted 2019/20 Capital
Improvement Program to cover the contract costs (Attachment B).
Town-wide Bicycle Master 2 February 4, 2020
Plan, CIP No. C-609
RECOMMENDATION
Adopt Resolution No. 5-2020, authorizing a Professional Services Agreement to develop
and prepare a Town-wide Bicycle Master Plan, CIP No. C-609.
Prepared by:
Thomas Valdriz
Program Analyst
Reviewed by:
Tai J. Williams
Assistant Town Manager
Attachments: A - Resolution No. 5-2020
B - CIP Page No. C-609
RESOLUTION NO. 5-2020
AUTHORIZING A PROFESSIONAL SERVICES AGREEMENT TO DEVELOP
AND PREPARE A TOWN-WIDE BICYCLE MASTER PLAN,
CIP NO. C-609
WHEREAS, the Danville Town Council previously appropriated funding for the Town-
wide Bicycle Master Plan, CIP No. C-609, in the adopted 2019/20 Capital Improvement
Program; and
WHEREAS, the Town circulated a Request for Proposal (RFP) to select the most qualified
and experienced consultant firm to prepare a Town-wide Bicycle Master Plan; and
WHEREAS, the Town issued the RFP on November 21, 2019 and received two (2)
proposals by January 6, 2020; and
WHEREAS, Alta Planning + Design, Inc. of Oakland, CA was determined to be the most
qualified consultant; and
WHEREAS, sufficient funds have been appropriated in the Capital Improvement
Program for Town-wide Bicycle Master Plan, CIP No. C-609; now, therefore, be it
RESOLVED, by the Danville Town Council that the Town Manager be and hereby is
authorized to execute in duplicate, on behalf of the Town, the Professional Services
Agreement with Alta Planning + Design, Inc. of Oakland, CA with a not-to-exceed budget
of $75,000.
APPROVED by the Danville Town Council at a regular meeting on February 4, 2020, by
the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
MAYOR
APPROVED AS TO FORM: ATTEST:
CITY ATTORNEY CITY CLERK
DocuSign Envelope ID: 379ACD03-0621-4E0C-B688-F70D10F2F243
ATTACHMENT A
www.danville.ca.govCIP116
Projects
TOWN-WIDE BICYCLE MASTER PLAN
PROJECT DESCRIPTION AND LOCATION:
DESCRIPTION OF MODIFICATIONS:
RATIONALE FOR PROPOSED PROJECT:
Study will provide guidance for implementation of programs,
projects and policies related to bicycle safety and infrastructure.
EXPECTED IMPACT ON OPERATING BUDGET:Additional worker hours required to maintain per year:0
Additional Town direct operating costs per year:$0
PROJECT COST ESTIMATE
PROJECT APPROPRIATION AND FUNDING
This project consists of the development of a comprehensive Bicycle
Master Plan to support, encourage and enhance bicycle travel in Danville.
The Master Plan will support and serve as a mechanism to set forth
implementation measures of the Goals and Policies defined in the Town's
General Plan related to multi-modal circulation, complete streets and
mobility and neighborhood quality.
4/19/2019PRINTED ON:
CIP No:C-609 STATUS:Adopted PRIORITY:2 PROJECT MANAGER:AD GREEN PROJECT:No
2019/20Prior Years 2020/21 2021/22 2022/23 2023/24 TotalExpenditure Category
Design/Plan Review $0 $0 $0 $0$75,000 $75,000$0
Construction $0 $0 $0 $0$0 $0$0
Inspection & Admin.$0 $0 $0 $0$0 $0$0
$75,000 $0 $0 $0 $0 $0 $75,000Total Cost Estimate:
$0Total Expenditure: Unexpended: $75,000 on 3-25-2019
2019/20Prior Years 2020/21 2021/22 2022/23 2023/24 TotalFunding Source(s)
Meas J-CC-TLC (2017)$75,000 $0 $0 $0 $0 $75,000$0
$75,000 $0 $0 $0 $0 $0 $75,000Total Funding:
www.danville.ca.govCIP116