RESOLUTION NO. 57-2019
AMENDING THE CONSTRUCTION CONTRACT FOR THE HAP MAGEE
RANCH PARK PLAYGROUND RENOVATION PROJECT,
CONTRACT NO. B-400
the Danville Town Council previously appropriated funding for the Hap
WHEREAS,
Magee Ranch Park Capital Maintenance, CIP No. B-400, Osage Station Park
Improvements, CIP No. B-490, and Osage Station Park Capital Maintenance, CIP No. B-
494 in the adopted 2019/20 Capital Improvement Program; and
the Town Council adopted Resolution No. 42-2019, awarding a construction
WHEREAS,
contract for the Hap Magee Ranch Park Playground Renovation Project to Suarez and
Munoz Construction, Inc; and
significant cost and time savings can be realized by initiating a change order
WHEREAS,
to the Hap Magee Ranch Park Playground Renovation Project for the improvements of
similar scope items at Osage Station Park; and
the total cost of the amendment exceeds the previously approved total
WHEREAS,
construction budget; and
the construction contract with Suarez and Munoz, Inc. needs to be amended
WHEREAS,
to increase the total authorized construction budget by $145,000, resulting in an amended
total construction budget of $858,770.50; and
sufficient funds have previously been appropriated by the Town Council in
WHEREAS,
Osage Station Park Improvements, CIP No. B-490 ($54,000) and Osage Station Park
Capital Maintenance, CIP No. B-494 ($91,000) to fund the contract amendment; now,
therefore, be it
by the Danville Town Council, that the City Engineer is hereby authorized
RESOLVED,
to execute, on behalf of the Town, a contract amendment in the amount of $145,000 with
Suarez and Munoz, Inc.
EpdvTjho!Fowfmpqf!JE;!:G135663.D9G8.5619.BDFC.9E739E989GCC
by the Danville Town Council at a regular meeting on September 3, 2019 by
APPROVED
the following vote:
AYES:
NOES:
ABSTAINED:
ABSENT:
MAYOR
APPROVED AS TO FORM: ATTEST:
CITY ATTORNEY CITY CLERK
PAGE 2 OF RESOLUTION NO. 57-2019