APPROVING A NOTICE OF COMPLETION FOR THE CENTRAL IRRIGATION
SYSTEM CAPITAL RECOVERY PROJECT PHASE II, CIP NO. A-492
WHEREAS, on December 16, 2014 the Town of Danville awarded a construction contract to
Bortolussi & Watkin, Inc., for the Central Irrigation System Recovery Project Phase II, CIP
No. A-492; and
WHEREAS, the City Engineer has determined that the work under this project has been
completed as of September 10, 2015, in accordance with the plans and specifications
thereof; and
WHEREAS, California Civil Code Section 9204 specifies the requirements for recordation
of a Notice of Completion; and
WHEREAS, not less than thirty days (30) nor more than forty-five (45) days after a Notice
of Completion is recorded the Town must release all undisputed retention withholdings to
the contractor; now, therefore, be it
RESOLVED,°by the Danville Town Council that said work by and with Bortolussi &
Watkin, Inc. is hereby accepted as complete; and, be it further
RESOLVED, that the City Clerk is hereby authorized and directed to file with the County
Recorder of the County of Contra Costa, a Notice of Completion for said project within
fifteen (15) days from the date hereof; and, be it further
RESOLVED, that undisputed retention withholdings be released in accordance with
Sections 8812 and 9356 of the California Civil Code.
APPROVED by the Danville Town Council at a regular meeting on October 6, 2015, by
the following vote:
AYES: Doyle, Stepper, Arnerich,
NOES: None
ABSTAINED: None
ABSENT: None
APPROVED AS TO FORM:
1
CITY ATTORNEY
Morgan, Storer
MAYOR
ATTEST:
CITY