HomeMy WebLinkAbout088-02RESOLUTION NO. 88-2002
APPROVING A NOTICE OF COMPLETION FOR THE PEDESTRIAN CURB
RAMPS 2002 PROJECT, CONTRACT NO. A-064(02)
WHEREAS, on June 11, 2002, the Town of Danville entered into a contract with Strange &
Chalmers, Inc. for the Pedestrian Curb Ramps 2002 Project, Contract lqo. A-064(02); and
WHEREAS, the City Engineer has determined that the work under this project has been
completed as of August 2, 2002, in accordance with the plans and specifications thereof; now,
therefore, be it
RESOLVED, by the Danville Town Council that said work by and with Strange & Chalmers,
Inc. is hereby accepted as complete; and, be it further
RESOLVED, that the City Clerk is hereby authorized and directed to file with the County
Recorder of the County of Contra Costa, a Notice of Completion for said project within ten (10)
days from the date hereof.
APPROVED by the Danville Town Council at a regular meeting on September 3, 2002, by the
following vote:
AYES:
NOES: None
ABSTAINED: None
ABSENT: Waldo
Arnerich, Doyle, Greenberg, Shimansky
VICE-MAYOR
APPROVED AS TO FORM:
CITY ATTORNEY
ATTEST:
CITY CLERK
NOTICE OF COMPLETION
Upon Recording Return to:
City Clerk
Town of Danville
510 La Gonda Way
Danville, CA 94526
NOTICE IS HEREBY GIVEN PURSUANT TO SECTION 3093 OF THE CALIFORNIA CIVIL CODE:
1. That on the 1 lth day of June, 2002, the Town of Danville, a municipal organization of the
State of California, did enter into a contract with:
Strange & Chalmers, Inc.
924 Lemon Street
Vallejo, CA 94590
as Contractor for certain improvement work: to wit,
Pedestrian Curb Ramps 2002 Project, Contract No. A-064(02)
Old Orchard Road between Thomhill Drive and Foxhall Court; St. Helena Drive between Canfield
Drive and Claridge Drive; Canfield Drive between St. Helena Drive, Farnum Court, and Camino
Ramon
2. That the surety upon the bond of the Contractor for said improvement work is:
Great American Insurance Company
That said improvement work was accepted by the Danville Town Council as completed
on the 3rd day of September, 2002
3. Contract Summary
Contract completed on August 2, 2002
Contract days allowed - 30, Extensions - 0
Total Days 7
Total Days 30
4. Original (As-Bid) Contract Amount
Total Change Orders (0)
Final Contract Amount
$32,767.50
0.00
$32,767.50
All work as described in the above named Contract between the above named Contractor and the Town of
Danville has been completed in accordance with plans and specifications. I verify, under penalty of
perjury, that ~s tree and correct.
"~SI~ak~, A~ Engineer
RCE #31870
cc: City Clerk, Engineering Department, Finance Department, Contractor
EXP 12-31-2004