HomeMy WebLinkAbout214-90RESOLUTION NO. 214-90 RESOLUTION OF AWARD OF CONTRACT FOR PHASE II - SYCAMORE VALLEY PARK, AND APPROPRIATING ADDITIONAL FUNDING FOR PROJECT CONSTRUCTION WHEREAS, the Town Council has previously approved bidding for the Phase II - Sycamore Valley Park project, contract no. 89-14; and WHEREAS, the City Clerk of the Town of Danville did, in open session on the 5th day of October publicly open and read aloud the sealed bids as required by law; and WHEREAS, the low bidder is Burdick Excavating Company, and the city Engineer has recommended awarding a contract for the project to said firm; and WHEREAS, the Town Council has determined that additive alternates 3,5,6,7 and 8 shall be included within the project scope; and WHEREAS, completion of the base park, construction contingency and construction of the identified additive alternate items will require an additional $480,536.50 in funding NOW, THEREFORE BE IT RESOLVED, by the Town Council of the Town of Danville, that the Town Manager is authorized to execute, on behalf of the Town, a written contract with Burdick Excavating Company for work in connection with Phase II - Sycamore Valley Park construction in the form as lodged with the City Clerk, together with such changes as may hereafter become necessary, provided such changes do not materially increase the obligations of the Town; and to receive and approve all bonds in connection therewith. NOW, THEREFORE BE IT FURTHER RESOLVED, that the Town Council of the Town of Danville appropriates, from previously unappropriated balances, $316,244.50 from the Park Fund and $164,292 from the Capital Improvement Program Fund - Residential T.I.P. Account to the Phase II - Sycamore Valley Park Account. MOVED AND APPROVED by the Town Council of the Town of Danville at the regular meeting of October 16, 1990 by the following vote: AYES: GREENBERG, LANE, RITCHEY, SCHLENDORF, SHIMANSKY NOES: NONE ABSTAINED: NONE ABSENT: NONE ~'/~ ATTEST: APPROVED AS TO FORM: ~ITY ATTORNEY EXHIBIT B PHASE II - SYCAMORE VALLEY PARK BID RESULTS Contractor Burdick Excavating Co. Watkin and Bortolussi Valley Crest Landscape Golden Bay Construction Gateway Landscape Construction Inc. Collishaw Construction B & B Concrete Inc. Base Bid $2,005,505 $2,048,131 $2,099,075 $2,156,169 $2,162,930 $2,196,944 $2,334,064 Add Alternates $488,500 $523,200 $394,740 $606,040 $557,520 $569,300 $559,184 Total $2,494,005 $2,580,641 $2,493,815 $2,762,208 $2,753,171 $2,766,294 $2,913,080 Project Estimate $1,981,436 $529,000 $2,510,436 EXHIBIT C ADDITIVE ALTERNATE ITEMS Item 1. PVC Fencing and band along Camino Tassajara 2. Concrete Paving at backstops, additional PCC paving at sport fields 3. Modular paving and concrete band at play area 4. Additional chain link fence and concrete mowband at sports field 5. Pond 6. Additional selected play equipment 7. Increase the size of selected 15 gal. trees to 24" box 8. Spray Pool 9. Little League baseball field area # 5 Total Cost Progect Estimate $ 28,000 $ 85,000 $ 27,000 $ 12,000 $205,000 $ 12,000 $ 170 ea. $ 50,000 $110,000 $529,000 Bid cost are based on the low bid received Bid Cost $ 20,000 $ 72,000 $ 26,000 $ 25,000 $175,000 $ 5,500 $ 0 $ 70,000 $ 95,000 $488,500