HomeMy WebLinkAbout2001-29RESOLUTION NO. 2001-29
APPROVING LAND USE PERMIT REQUEST LUP 2001-21 ALLOWING THE
ESTABLISHMENT AND USE OF A WIRELESS COMMUNICATION
FACILITY TO BE LOCATED IN THE SYCAMORE VALLEY
ROAD RIGHT-OF-WAY NEAR TUNBRIDGE ROAD
(SPRINT PCS)
WHEREAS, THE TOWN OF DANVILLE (Owner) and SPRINT PCS (Applicant) have request
approval of a Land Use Permit request (LUP 2001-21 ) to allow the establishment of a wireless
communication facility; and
WHEREAS, the facility would be located within the Town public right-of-way on an existing
light pole with equipment to be located in the roadside landscape and would include two panel
antennas mounted on the pole and four small equipment cabinets mounted on the retaining wall
on the south side of Sycamore Valley Boulevard; and
WHEREAS, the Town of Danville Wireless Communication Ordinance requires approval of a
Land Use Permit prior to the operation of a wireless communication facility; and
WHEREAS, the Planning Commission did review the project at a noticed public hearing on
October 9, 2001; and
WHEREAS, the project has been found to be Categorically Exempt from the requirements of the
California Environmental Quality Act (CEQA); and
WHEREAS, the public notice of this action was given in all respects as required by law; and
WHEREAS, a staff report was submitted recommending that the Planning Commission approve
the request; and
WHEREAS, the Planning Commission did hear and consider all reports, recommendations, and
testimony submitted in writing and presented at the hearing; now, therefore, be it
RESOLVED that the Planning Commission of the Town of Danville approves Land Use Permit
request LUP 2001-21 per the conditions contained herein, and makes the following findings in
support of this action:
The proposed land use will not be detrimental to the to the health, safety, and general
welfare of the Town.
2, The land use will not adversely affect the orderly development of property within the
Town.
The land use will not adversely affect the preservation of property values and the
protection of the tax base within the Town.
The land use will not adversely affect the policy and goals as set by the 2010 General
Plan.
The land use will not create a nuisance and\or enforcement problem within the
neighborhood or community.
6. The land use will not encourage marginal development within the neighborhood.
CONDITIONS OF APPROVAL
This approval is for a Land Use permit request LUP 2001-21 authorizing the
establishment and operation of a wireless communication facility located within the Town
public right-of-way on an existing light pole with equipment to be located in the roadside
landscape and would include two panel antennas mounted on the pole and four small
equipment cabinets mounted on the retaining wall on the south side of Sycamore Valley
Boulevard. Except as may be modified by the conditions contained herein, development
shall be substantially as shown on the project drawings labeled "Sprint PCS Central
Danville," as prepared by ATI Architects and Engineers, dated received by the Planning
Division on June 15, 2001.
The applicant shall pay or be subject to any and all Town and other related fees that the
property may be subject to. These fees shall be based on the current fee schedule in effect
at the time the relevant permits are secured, and shall be paid prior to issuance of said
permit and prior to any Town Council final approval action.
Prior to the issuance of a building permit, the applicant shall reimburse the Town for
notifying surrounding neighboring residents of the public hearing. The fee shall be
$120.75 (161 notices X $0.75 per notice).
The applicant shall submit to the Town of Danville fees required to file a Notice of
Determination for this project as required by AB 3185. The fee shall be $25.00.
Prior to issuance of a building permit, the applicant shall submit a written report in
compliance with the conditions of approval of this project for the review and approval of
PAGE 2 OF RESOLUTION NO. 2001-29
the Planning Division. This report shall list each condition of approval followed by a
description of what the applicant has provided as evidence of compliance with that
condition. The report must be signed by the applicant. The report may be rejected by the
Town if it is not comprehensive with respect to the applicable conditions of approval.
The project shall be constructed as approved. Minor modifications in the design, but not
the use, may be approved by staff. Any other change will require Planning Commission
approval through a separate Land Use Permit application.
The applicant shall obtain a building permit from the Town's Building Division prior to
installation of the equipment and antennas.
The applicant shall allow additional wireless communication companies to collocate
antenna equipment and antennas at this site, subject to review and approval by the
Planning Commission under a separate Land Use Permit and/or Development Plan
application. The applicant and other wireless carriers shall provide a mechanism for the
construction and maintenance of shared facilities and infrastructure and shall provide for
equitable sharing of costs. Construction of future facilities shall not interrupt or interfere
with the continuous operation of the applicant's facilities.
Any expansion or modification of the use shall be subject to review and approval by the
Planning Division under a separate Land Use Permit and/or Development Plan
application.
10.
At any time during the effectiveness of this approval, the approval shall be revocable for
cause in accordance with sections 26-2.2022 and 418.1 of the Danville Municipal Code,
including failure to comply with these conditions of approval if the permittee has caused
or permitted any public nuisance in connection with the use.
11.
Prior to the Town's issuance of a building permit for the project, the applicant shall enter
into a lease agreement with the Town for use of Town property for this facility.
12.
This Land Use Permit shall be valid for a time period of five years. Additional time
extensions, with a maximum period of five years per extension, may be approved by the
Chief of Planning, upon the receipt ora letter requesting the extension by the applicant.
Such extension shall be based on a determination that the findings made for approval of
the land are still valid. At the discretion of the Chief of Planning, the extension request
may be referred to the Planning Commission for consideration and action.
PAGE 3 OF RESOLUTION NO. 2001-29
13.
All equipment associated with a wireless communication facility shall be removed within
30 days of the discontinuation of the use and the site shall be restored to its original pre-
construction condition. Prior to installation of the facility, the service provider shall
submit to the Town a letter stating the provider's agreement to remove the equipment
within 30 days of discontinued use of the facility. In addition, the service provider shall
provide the Town with a notice of intent to vacate a site a minimum of 30 days prior to the
vacation.
14.
The panel antennas shall be painted to match the light pole. The equipment cabinets shall
be painted to match surrounding landscaping, subject to review and approval by the
Planning Division prior to issuance of building permits for the project.
15.
The applicant is not authorized to trim any trees or remove any landscaping as part of this
project as part of this project. Any trimming/removal of plant material will be allowed
only after receiving written approval by the Town.
16.
The applicant must obtain an encroachment permit for the work related to this project
prior to the issuance of building permits.
17.
The GPS antenna proposed to be located on the sound wall on the south side of the street
shall be re-located to be located on the same light pole as the facility's panel antennas.
APPROVED by the Danville Planning Commission at a regular meeting on October 9, 2001 by
the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
Combs, Graham, Jameson, Legg, Moran, Storer, Osborn
APPROVED AS TO FORM:
PAGE 4 OF RESOLUTION NO. 2001-29