RESOLUTION NO. 96-41
A RESOLUTION OF THE PLANNING COMMISSION OF THE TOWN OF DANVILLE
APPROVING LAND USE PERMIT REQUEST LUP 96-23
AND DEVELOPMENT PLAN REQUEST DP 96-15 ALLOWING
THE ESTABLISHMENT AND USE OF A WIRELESS COMMUNICATION FACILITY
(APN: 197-100-042 -- NEXTEL COMMUNICATIONS @ EL PINTO)
WHEREAS, Nextel Communications has requested approval of Land Use Permit and
Development Plan requests to allow the establishment and operation of a wireless
communication facility on a 2.9 +/- acre site within a Town identified Major Ridgeline area;
and
WHEREAS, the subject site is located at 246 E1 Pinto Road and is further identified as
Assessor's Parcel Number 197-100-042; and
WHEREAS, the Town of Danville R-100; Single Family Residential District requires approval
of Land Use Permit prior to the establishment or operation of wireless communication
facility; and
WHEREAS, the Town of Danville Major Ridgeline and Scenic Hillside Development
Ordinance (Ordinance 29-84) requires approval of a Development Plan application prior
to placement of the facility within a Town identified Major Ridgeline area; and
WHERFa~S, the Planning Commission did review the project at a noticed public hearing on
September 24, 1996; and
WHEREAS, the public notice of this action was given in all respects as required by law; and
WHEREAS, a staff report was submitted recommending that Planning Commission approve
the request; and
WHERF~S, the Planning Commission did hear and consider all reports, recommendations,
and testimony submitted in writing and presented at the hearing; now, therefore, be it
PAGE I OF RESOLUTION NO. 96-41
RESOLVED that the Planning Commission of the Town of Danville approves of the Land Use
Permit request LUP 96-23 and Development Plan request DP 96-15 per the conditions
contained herein, and makes the following findings in support of this action:
Land Use Permit Findings:
The proposed land use will not be detrimental to the to the health, safety, and general
welfare of the Town.
The land use will not adversely affect the orderly development of property within the
Town.
3. The land use will not adversely affect the preservation of property values and the
protection of the tax base within the Town.
4. The land use will not adversely affect the policy and goals as set by the General Plan.
5. The land use will not create a nuisance and~or enforcement problem within the
neighborhood or community.
6. The land use will not encourage marginal development within the neighborhood.
7. That special conditions or unique characteristics of the subject property and its
location or surroundings are established. Failure to so find shall result in a denial.
Development Plan Findings:
1. The proposed siting and design of the new structure will not conflict with the intent
and purposes of Ordinance 29-84 ("Scenic Hillside and Major Ridgeline
Developmenf'), in that development will be achieved with minimal grading and will
not adversely impact predominate views of a Town-identified Scenic Hillside or
Major Ridgeline area.
2. The proposed development is in conformance with the goals and policies of the
General Plan.
o
The proposed development is in conformance with the zoning district in which the
property is located.
PAGE 2 OF RESOLUTION NO. 96-41
CONDITIONS OF APPROVAL
This approval is for a Land Use Permit request (LUP 96-23) and Development Plan
request (DP 96-15) authorizing the establishment and operation of a wireless
communication facility. Except as may be modified by the conditions contained
herein, development shall be substantially as shown on the project drawings labeled
"Nextel Communications -- Boon Hill," as prepared by Erkan & Associates, consisting
of four sheets, and dated received by the Planning Division on September 18, 1996.
The applicant shall pay any and all Town and other related fees that the property may
be subject to. These fees shall be based on the current fee schedule in effect at the
time the relevant permits are secured, and shall be paid prior to issuance of said
permit and prior to any Town Council final approval action.
The applicant shall obtain a building permit from the Town's Building Division prior
to installation of the equipment and antennas.
All antennas and outdoor equipment shall be painted a color to blend with
surrounding vegetation and shall not have a reflective finish. Prior to the issuance
of a building permit, the applicant shall submit color samples to the Planning
Division for review and approval. The visual appearance of the antennas shall be
maintained in their approved condition.
The proposed outdoor air conditioning unit shall be insulated for noise impacts to
the satisfaction of the Planning Division. Prior to the issuance of a building permit,
the applicant shall submit construction plans detailing the proposed materials and
method of insulation for the review and approval by the Planning Division.
o
If feasible, the applicant shall allow additional wireless communication companies
to collocate antenna equipment and antennas at this site, subject to review and
approval by the Planning Commission under a separate Land Use Permit application.
The applicant and other wireless carriers shall provide a mechanism for the
construction and maintenance of shared facilities and infrastructure and shall
provide for equitable sharing of costs. Construction of future facilities shall not
interrupt or interfere the continuous operation of the applicant's facilities.
Any expansion or modification of the use shall be subject to review and approval by
the Planning Division under a separate Land Use Permit application.
PAGE 3 OF RESOLUTION NO. 96-41
The project shall be constructed as approved. Minor modifications in the design, but
not the use, may be approved by the Planning Division. Any other change will
require Planning Commission approval through a separate Land Use Permit
application.
At any time during the effectiveness of this approval, the approval shall be revokable
for cause in accordance with sections 26-2.2022 and 418.1 of the Danville Municipal
Code, including failure to comply with these conditions of approval if the permittee
has caused or permitted any public nuisance in connection with the use.
10.
This Land Use Permit shall be valid for a time period of five years. Additional time
extensions, with a maximum period of five years per extension, may be approved by
the Chief of Planning, upon the receipt of a letter requesting the extension by the
applicant. Such extension shall be based on a determination that the findings made
for approval of the land use are still valid. At the discretion of the Chief of Planning,
the extension request may be referred to the Planning Commission for consideration
and action.
11.
All equipment associated with a wireless communication facility shall be removed
within 30 days of the discontinuation of the use and the site shall be restored to its
original preconstruction condition. Prior to installation of the facility, the service
provider shall submit to the Town a letter stating the provider's agreement to remove
the equipment within 30 days of discontinued use of the facility. In addition, the
service provider shall provide the Town with a notice of intent to vacate a site a
minimum of 30 days prior to the vacation.
PAGE 4 OF RESOLUTION NO. 96-41
APPROVED by the Danville Planning Commission at a Regular Meeting on September 24,
1996, by the following vote:
AYES:
NOES: -
ABSENT: -
ABSTAINED: Hunt
Bowlby, Combs, Jameson, Moran, Osborn, Murphy
APPROVED AS TO FORM:
City Attorney
ptwz05.wpd