HomeMy WebLinkAboutDP 87-19 EXHIBIT A
FINDINGS & CONDITIONS OF APPROVAL
279 Front Street - DP 87-19
FINDINGS
Development Plan
The proposed project is in conformance with the Downtown
Master Plan.
The proposed project is in conformance with the RB-S2 zoning
regulations and design standards for office development.
The proposed project is in compliance with the goals and
intent of the Downtown Parking District by retaining a
maximum number of parking spaces on the site.
The proposed project is planned to integrate with adjacent
development and will not have an adverse impact on
neighboring property owners.
Variance
A' height variance to allow a 41 maximum foot high structure
is allowed in order to permit the proposed project to match
the floor elevation of the existing structure.
The second story building elevation is designed to be
integrated into the roof structure which will reduce the
visual impact and apparent height of the building.
The building height is minimized through removal of all roof
mounted mechanical equipment. All such equipment will be
contained within the second story of the building.
The addition is well screened by surrounding tree cover and
by the existing building.
The 13' 6" open clearance above parking reduces the apparent
mass of the building.
CONDITIONS OF APPROVAL
A. General
The development shall be substantially as shown on the
project drawings labeled addition to law offices for
Parkside Associates, as prepared by Jerry Loving &
Assocla%e~ ~a%e~ 1/~/~ and ma~k~d ~hibit I~Cll on file
with the Planning Department except as modified by the
following conditions of approval·
lC
The developer shall pay any and all City and other
related fees that the property may be subject to.
These fees shall be based on the current fee schedule
in effect at the time the relevant permit is secured.
Notice should be taken specifically of the City's
Transportation Improvement Program (TIP) fee and the
drainage acreage fee as established by the Flood
Control District.
The developer shall comply with all requirements of the
San Ramon Valley Fire Protection District and the San
Ramon Valley Unified School District.
If archeological materials are uncovered during any
construction or pre-construction activities on the
site, all earthwork within 100 feet of these materials
shall be stopped until a professional archeologist
certified by the Society of California Archeology
and/or the Society of Professional Archeology has had
an opportunity to evaluate the significance of the find
and to suggest appropriate mitigation measures, if they
are deemed necessary.
Construction and grading operations shall be limited to
weekdays (Mondays through Fridays) during the hours
from 7:30 a.m. to 5:30 p.m., unless otherwise approved
in writing by the city Engineer. The developer shall
be responsible for providing security to the site
during the construction phase of the project.
The developer shall pay the applicable drainage area 10
fee.
B. Site Planning
Ail lighting shall be installed in such a manner that
glare is directed away from surrounding properties and
rights-of-way.
The location of any pad mounted transformers shall be
subject to approval by the Planning Department prior to
the issuance of a building permit. Generally speaking,
such transformers shall not be located between any
street and the front of a building.
The developer shall fund the design and installation of
a fire hydrant and service line on the adjacent
municipal parking lot at the time of construction of
2C
the municipal parking lot. The location of the fire
hydrant is subject to approval by the City Engineer and
the Fire District.
C. Landscaping
A final landscaping plan shall be submitted for review
and approval by the Planning Department prior to the
issuance of a building permit.
Ail plant material shall be served by an automatic
underground irrigation system and maintained in a
healthy growing condition.
Ail trees shall be a minimum of 15 gallon container
size and properly staked. Shrubs not used as ground
cover shall be a minimum of 5 gallons is size.
Ail landscaped areas not covered by shrubs and trees
shall be planted with live ground cover.
Ail existing trees on the site shall be preserved to
the extent practicable: removal will be allowed only
upon written approval of the Planning Department as
indicated on final plans.
Additional redwood trees shall be planted along the
northwest boundary of the site to screen the building
from the adjacent property and areas to the west.
D. Architecture
Ail ducts, meters, air conditioning and/or any other
mechanical equipment whether on the structure or on the
ground shall be effectively screened from view with
landscaping or materials architecturally compatible
with the main structure(s). The highest point of any
roof mounted equipment shall not extend above the top
of the equipment well.
Ail trash and refuse shall be contained within
enclosures architecturally compatible with the main
structure(s). Enclosure design shall include six (6)
foot high masonry walls on three sides with steel
framed gates and wood bolted to the gates. Gates will
be self-closing and self-latching.
The street number(s) of the building(s) shall be posted
so as to be easily seen from the street at all times,
day and n~h~.
3C
Ee
If additional signing for the development is desired,
in addition to the existing signage, a comprehensive
sign program shall be submitted to the City for
consideration under a separate application.
Final colors and materials shall match the materials on
the existing building.
6. The roofing material must be class A or B.
Parking
Ail parking spaces shall be striped and provided with
wheel stops unless they are fronted by concrete curbs,
in which case sufficient areas shall be provided beyond
the ends of all parking spaces to accommodate the
overhang of automobiles.
Where authorized, compact car spaces shall be clearly
designated with appropriate pavement marking or
signage. Compact spaces shall be no less than 8 feet
by 16 feet in size including allowable overhang.
Grading
Any grading on adjacent properties will require written
approval of those property owners affected.
Areas undergoing grading, and all other construction
activities shall be watered, or treated with other dust
control measures to prevent dust. These measures shall
be approved by the City Engineer and employed at all
times as conditions warrant.
Streets
The developer shall obtain an encroachment permit from
the Engineering Department prior to commencing any
construction activities within any public right-of-way
or easement.
Ail street signing shall be installed by the developer
as required by the City. This shall include, but is
not necessarily limited to "Stop," "No Parking," "Not a
Through Street," and street name signs. Traffic signs
and parking restriction signs shall be approved by the
Engineering Department. The applicant shall paint the
curb red and post "No Stopping" signs south of the
southerly driveway.
The developer shall keep adjoining public streets free
and clean of project dirt, mud, materials and debris
during the construction period, as is found necessary
by the City Engineer.
Handicapped ramps shall be provided and located as
required by the city Engineer.
Ho
So
This development shall be provided with a safe and
effective circulation system for bicycles and
pedestrians. These facilities shall be designed and
installed to the satisfaction of the City Engineer and
shall be separated from vehicular traffic wherever
possible.
e
Any damage to street improvements now existing or done
during construction on or adjacent to the subject
property shall be repaired to the satisfaction of the
City Engineer at full expense to the developer. This
shall include slurry seal, overlay or street
reconstruction if deemed warranted by the city
Engineer.
Landscaping shall not obstruct the sight distance at
the driveway or within the parking lot.
Infrastructure
Drainage facilities and easements shall be provided to
the satisfaction of the City Engineer and/or the Chief
Engineer of the Contra Costa County Flood Control
District.
Ail storm water run-off shall be collected and
conducted via an approved drainage method to the
nearest approved downstream facility on Front Street.
Off-site drainage flows shall be intercepted at the
project boundary via an approved storm drain facility,
or as approved by the Town.
Roof drains shall empty onto paved areas, concrete
swales, other approved dissipating devices, or into a
pipe.
Concentrated drainage flows shall not be permitted to
cross sidewalks or driveways.
The developer shall comply with all relevant
requirements of the Contra Costa County Flood Control
District and the Department of Fish and Game.
If a storm drain must cross a lot, or be in an easement
between lots, the easement shall be equal to or at
least double the depth of the storm drain.
The developer shall furnish proof to the city Engineer
of the acquisition of all necessary rights of entry,
5C
permits and/or easements for the construction of off-site
temporary or permanent road and drainage improvements.
Ail new utilities required to serve the development
shall be installed underground.
10.
Ail public improvement plans shall be prepared by a
licensed civil engineer.
11.
The developer shall mitigate the impact of additional
storm water runoff from this development on the
downstream creek by either of the following methods:
Removing 1 cubic yard of channel excavation
material from the inadequate portion of San Ramon
Creek near Chaney Road for each 50 square feet of
new impervious surface area created by the
development. All excavating material shall be
disposed of offsite by the developer at his cost.
The site selection, land rights, and construction
staking will be by the Flood Control District.
OR AT THE OPTION OF THE DEVELOPER
Contribute to the County Deficiency Development
Fee Trust (Fund No. 812100-0800) a drainage fee of
$0.10 per square feet of new impervious surface
area created by the development. Within 12 months
of receipt of the contribution, the Flood Control
District will use the monies to implement the
subject improvements. The added impervious
surface area created by the development will be
based on the Flood Control District's standard
impervious surface area ordinance.
Approved by the Town of Danville
Planning Commission on January 25, 1988
lanningCommission
6C