HomeMy WebLinkAbout90-20 ORDINANCE NO. 90-20
AN ORDINANCE OF THE TOWN OF DANVILLE REPEALING AND ADDING CERTAIN
SECTIONS OF ARTICLE 26-2.28 (FEES) OF THE DANVILLE MUNICIPAL CODE
REGARDING FEES FOR PLANNING AND RELATED SERVICES.
THE TOWN COUNCIL OF THE TOWN OF DANVILLE DOES ORDAIN AS FOLLOWS:
SECTION 1. Purpose. The Town Council has determined that the
present fees for those services are inadequate to cover the
Town's reasonable cost of providing the services. It is
necessary for the Town to revise its fee schedule to insure
that charges compare more directly to the cost of processing
services provided by the Town and to insure that the fees
collected are both reasonable and non-discriminatory. Town
staff has evaluated the costs of providing planning and
related services and has recommended a revised fee schedule.
SECTION 2. Findinq. Due to the wide variety of Town planning,
engineering and related services provided and because the
scope and complexity of each project and application differ,
the actual cost of providing services cannot be determined
precisely. The fees established herein represent the
estimated reasonable cost of providing services for which the
fees are charged.
SECTION 3. Fee Schedule - Specific. Section 26-2.2803(b) of the
Danville Municipal Code is hereby amended to read as follows:
"Section 26-2.2803(b). Amount of Fee. Depending upon the
request, the fee for service shall be as follows:
ENGINEERING SERVICE FEE FOR SERVICE
1. Map Check 2-10 lots $1000+$100/lot
Review of parcel/final map. 11 greater $2000+$10/lot
2. Improvement Plan Check 3.5% of projects less
Reviews of improvement plans than $50K
for street and drainage 3.25% of projects
improvements. $50K to $100K
3% of projects $100K
and above.
3. Engineering Inspection 5.5% of projects less
Inspection of installation than $50K
of street and drainage 5.25% of projects
improvements. $50K to $100K
5% of projects $100K
and above.
1
4. Street Liqhting One year operational
Operation of public street cost + 10%.
lighting system.
5. Encroachment Permit $80 minimum of 5.5%
Work within public of construction cost
right-of-way. of large projects.
6. Drainaqe Permit $80 minimum or 5.5%
Work within any of construction cost
drainage easement. of large projects.
PLANNING SERVICES FEE FOR SERVICE
1. Environmental Assessment
Initial Study*
(Standard Neg. Dec.) $100
Initial Study
(Mitigated Neg. Dec.) $275
Environmental Impact
Report No Change (Cost + 30%)
* Unless qualifying for a categorical exemption pursuant to
CEQA, all projects must undergo an initial study.
2. Certificate of
Zoning Compliance $25
3. Development Plan
Scenic Hillside $275
Major Ridgeline $800
Administrative
(No Public Hrg.) $275*
* This fee may be reduced to $100 by the Director of
Development Services Department in cases of minor additions to
residential structures.
Minor Development Plan
(W/ Public Hrg.) $800
Multi-Family Resid. $1625 +$55/unit
Commercial, office,
Industrial $1625
4. Land Use Permit
Antenna/Satellite Dish $50
Temporary Land Use $100
Downtown Conditional Use $100
Child Care or Day Care
Facility (7-12) $100
Child Care or Day Care
Facility (12+) $275
~cond uni~ $225
2
PLANNING SERVICES FEE FOR SERVICE
Administrative Minor Land
Use Permit(No Public Hrg) $275
Commercial, office or
Industrial
$800
Residential Care Facl. $1625 +$55/bed
LUP/DP Combination $275
5. Subdivision
Major Subdivision (more
than four lots) $1625 base fee +;
$80/du for 1-50
$55/du for 51-250
$12/du for 251 +
Minor Subdivision (four
or fewer lots) $1085
Tentative Map Extension $225
6. Rezoning
Agricultural $435
Residential $2700
Commercial, office or
Industrial $2700
7. Planned Unit Development District
A. Preliminary Development Plan
Residential $1625 base fee +;
$80/du for 1-50
$55/du for 51-250
$12/du for 251+
Commercial, office
or Industrial $2700 base fee +;
$220/acre or ptn
B. Final Development Plan $1085,
* If substantially the same as Preliminary Development Plan,
this fee may be reduced 30% by the Director of Development
Services Department.
8. Variance
Administrative $100
Non-administrative $275
9. Sign Review
- Administrative $100
~on-a~mlni~ativ~ $165
PLANNING SERVICES FEE FOR SERVICE
10. Home Occupation Permit $100
11. General Plan Amendment $2700 base fee +;
$80/ac. for 1-15
$55/ac. for 16-50
$27/ac. for 51+
12. Design Review Board
Administrative (No Public
Hearing Involved) $50
Non-administrative (Requires
Public Hearing) $250
13. Agricultural Preserve
Rezoning $810
Contract Cancellation
$540
14. Lot Line Adjustment
$275 per lot
15. Time Extension $100
16. Appeals $100
17. Building Permit
Plan Check $5 for all permits for
valuations up to
$15,000, thereafter fee
shall be $10 for each
$100,000 valuation or
portion thereof, up to a
maximum fee of $100
18. Special Planning
Studies Cost + 30%
19. Parcel Merger $275 per lot
* - Unless qualify for a categorical exemption pursuant to CEQA,
all projects must undergo an initial study.
The legislative body may amend this fee schedule annually.
4
SECTION 4. Codification. Only Section 3 hereof shall be codified
in the Danville Municipal Code.
The foregoing Ordinance was introduced at a meeting of the
Town Council of the Town of Danville held on October 16, 1990 and
was adopted and ordered published at a meeting of the Council held
on November 6 , 1990, by the following vote:
AYES: GREENBERG, LANE, RITCHEY, SCHLENDORF, SHIMANSKY
NOES: NONE
ABSTAIN: NONE
ABSENT: NONE
CLE CITY ATTORNEY
osrgll06
5